170 Ind. Admin. Code 5-3-2.5

Current through November 6, 2024
Section 170 IAC 5-3-2.5 - Construction packets

Authority: IC 8-1-1-3; IC 8-1-22.5-4

Affected: IC 8-1-2; IC 8-1-22.5

Sec. 2.5.

At a construction site (as defined in section 4(e)(4) of this rule), the operator shall maintain on-site or have access to the following documentation and provide it to the division upon request:

(1) Maps or drawing of the project, including both existing and proposed facility information.
(2) Information regarding type, size, and length of pipe and appurtenances to be used for the installation.
(3) Information sufficient to establish that the operator or its contractor appropriately notified Indiana 811 of the construction.
(4) As-built drawings of the construction project for any section of facilities placed in service or facilities installed.
(5) Installation location of valves and pertinent information to include but not be limited to:
(A) drawings with measurements;
(B) types of valves; or
(C) manufacturer of valves.
(6) Construction scope of work, which may include:
(A) a project overview, with a brief statement describing the purpose of the project; or
(B) a project timeline, with the anticipated duration of the project, and proposed start date, if known.
(7) Requirements and records for proposed and actual pressure tests, including maximum allowable operating pressure (MAOP) requirements.
(8) Evidence that corrosion control impacts have been reviewed.
(9) Upon request by the division, the operator shall provide evidence that the operator is complying with its distribution integrity management program (DIMP) plan in accordance with gaining information over time through normal activities conducted on a pipeline (49 CFR 192.1007(a)(3)) .

170 IAC 5-3-2.5

Indiana Utility Regulatory Commission; 170 IAC 5-3-2.5; filed 3/17/2022, 12:34 p.m.: 20220413-IR-170210213FRA