170 Ind. Admin. Code 5-3-2.3

Current through November 6, 2024
Section 170 IAC 5-3-2.3 - Pre-tested pipe

Authority: IC 8-1-1-3; IC 8-1-22.5-4

Affected: IC 8-1-2; IC 8-1-22.5

Sec. 2.3.

When an operator installs a pipeline that was previously pressure tested, a written record of the previous pressure test for each pipe section must be available or the operator must pressure test the pipeline after installation prior to being energized according to 49 CFR 192 Subpart J by another method allowed by this rule.

170 IAC 5-3-2.3

Indiana Utility Regulatory Commission; 170 IAC 5-3 - 2.3; filed 3/17/2022, 12:34 p.m.: 20220413-IR-170210213FRA