S.D. Codified Laws § 49-41B-5

Current through the 2024 Legislative Session
Section 49-41B-5 - Notification of intent to apply for permit required before filing application-Time-Prefiling conference if applicant requests

A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in § 49-41B-11. A prefiling conference may be requested by the applicant and such request shall be granted by the commission.

SDCL 49-41B-5

SL 1977, ch 390, § 5; SL 2006, ch 242, §2.