A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in § 49-41B-11. A prefiling conference may be requested by the applicant and such request shall be granted by the commission.
SDCL 49-41B-5