Current through the 2023 Regular Session
Section 82-4-335 - Operating permit - limitation - fees(1) A person may not engage in mining, ore processing, or reprocessing of tailings or waste material, construct or operate a hard-rock mill, use cyanide ore-processing reagents or other metal leaching solvents or reagents, or disturb land in anticipation of those activities in the state without first obtaining a final operating permit from the department. Except as provided in 82-4-343, a separate final operating permit is required for each complex.(2) A small miner who intends to use a cyanide ore-processing reagent or other metal leaching solvents or reagents shall obtain an operating permit for that part of the small miner's operation where the cyanide ore-processing reagent or other metal leaching solvents or reagents will be used or disposed of.(3)(a) Prior to receiving an operating permit from the department, a person shall pay the basic permit fee of $500. The department may require a person who is applying for a permit pursuant to subsection (1) to pay an additional fee not to exceed the actual amount of contractor and employee expenses beyond the normal operating expenses of the department whenever those expenses are reasonably necessary to provide for timely and adequate review of the application, including any environmental review conducted under Title 75, chapter 1, parts 1 and 2. The department may further define these expenses by rule. Whenever the department determines that an additional fee is necessary and the additional fee will exceed $5,000, the department shall notify the applicant that a fee must be paid and submit to the applicant an itemized estimate of the proposed expenses. The department shall provide the applicant an opportunity to review the department's estimated expenses. The applicant may indicate which proposed expenses the applicant considers duplicative or excessive, if any.(b)(i) Subject to subsection (3)(b)(ii), a contractor shall, at the request of the applicant, directly submit invoices of contractor expenses to the applicant.(ii) A contractor's work is assigned, reviewed, accepted, or rejected by the department pursuant to this section.(4) The person shall submit an application on a form provided by the department, which must contain the following information and any other pertinent data required by rule: (a) the name and address of the operator, the engineer of record if applicable, and, if a corporation or other business entity, the name and address of its officers, directors, owners of 10% or more of any class of voting stock, partners, and the like and its resident agent for service of process, if required by law;(b) the minerals expected to be mined;(c) a proposed reclamation plan;(d) the expected starting date of operations;(e) a map showing the specific area to be mined and the boundaries of the land that will be disturbed, the topographic detail, the location and names of all streams, roads, railroads, and utility lines on or immediately adjacent to the area, and the location of proposed access roads to be built;(f) the names and addresses of the owners of record and any purchasers under contracts for deed of the surface of the land within the permit area and the owners of record and any purchasers under contracts for deed of all surface area within one-half mile of any part of the permit area, provided that the department is not required to verify this information;(g) the names and addresses of the present owners of record and any purchasers under contracts for deed of all minerals in the land within the permit area, provided that the department is not required to verify this information;(h) the source of the applicant's legal right to mine the mineral on the land affected by the permit, provided that the department is not required to verify this information;(i) the types of access roads to be built and manner of reclamation of road sites on abandonment;(j) a plan that will provide, within limits of normal operating procedures of the industry, for completion of the operation;(k) ground water and surface water hydrologic data gathered from a sufficient number of sources and length of time to characterize the hydrologic regime;(l) a plan detailing the design, operation, and monitoring of impounding structures, including but not limited to tailings impoundments and water reservoirs, sufficient to ensure that the structures are safe and stable. For a tailings storage facility, this requirement is met by submission of a design document pursuant to 82-4-376, a panel report pursuant to 82-4-377, and a tailings operation, maintenance, and surveillance manual pursuant to 82-4-379 prior to issuance of a draft permit.(m) a plan identifying methods to be used to monitor for the accidental discharge of objectionable materials and remedial action plans to be used to control and mitigate discharges to surface or ground water;(n) an evaluation of the expected life of any tailings impoundment or waste area and the potential for expansion of the tailings impoundment or waste site. For a tailings storage facility, this requirement is met by submission of a design document pursuant to 82-4-376, a panel report pursuant to 82-4-377, and a tailings operation, maintenance, and surveillance manual pursuant to 82-4-379 prior to issuance of a draft permit.(o) an assessment of the potential for the postmining use of mine-related facilities for other industrial purposes, including evidence of consultation with the county commission of the county or counties where the mine or mine-related facilities will be located.(5) Except as provided in subsection (7), the permit provided for in subsection (1) for a large-scale mineral development, as defined in 90-6-302, must be conditioned to provide that activities under the permit may not commence until the impact plan is approved under 90-6-307 and until the permittee has provided a written guarantee to the department and to the hard-rock mining impact board of compliance within the time schedule with the commitment made in the approved impact plan, as provided in 90-6-307. If the permittee does not comply with that commitment within the time scheduled, the department, upon receipt of written notice from the hard-rock mining impact board, shall suspend the permit until it receives written notice from the hard-rock mining impact board that the permittee is in compliance.(6) When the department determines that a permittee has become or will become a large-scale mineral developer pursuant to 82-4-339 and 90-6-302 and provides notice as required under 82-4-339, within 6 months of receiving the notice, the permittee shall provide the department with proof that the permittee has obtained a waiver of the impact plan requirement from the hard-rock mining impact board or that the permittee has filed an impact plan with the hard-rock mining impact board and the appropriate county or counties. If the permittee does not file the required proof or if the hard-rock mining impact board certifies to the department that the permittee has failed to comply with the hard-rock mining impact review and implementation requirements in Title 90, chapter 6, parts 3 and 4, the department shall suspend the permit until the permittee files the required proof or until the hard-rock mining impact board certifies that the permittee has complied with the hard-rock mining impact review and implementation requirements.(7) Compliance with 90-6-307 is not required for exploration and bulk sampling for metallurgical testing when the aggregate samples are less than 10,000 tons.(8) A person may not be issued an operating permit if: (a) that person's failure, or the failure of any firm or business association of which that person was a principal or controlling member, to comply with the provisions of this part, the rules adopted under this part, or a permit or license issued under this part has resulted in either the receipt of bond proceeds by the department or the completion of reclamation by the person's surety or by the department, unless that person meets the conditions described in 82-4-360;(b) that person has not paid a penalty for which the department has obtained a judgment pursuant to 82-4-361;(c) that person has failed to post a reclamation bond required by 82-4-305; or(d) that person has failed to comply with an abatement order issued pursuant to 82-4-362, unless the department has completed the abatement and the person has reimbursed the department for the cost of abatement.(9) A person may not be issued a permit under this part unless, at the time of submission of a bond, the person provides the current information required in subsection (4)(a) and: (a)(i) certifies that the person is not currently in violation in this state of any law, rule, or regulation of this state or of the United States pertaining to air quality, water quality, or mined land reclamation; or(ii) presents a certification by the administering agency that the violation is in the process of being corrected to the agency's satisfaction or is the subject of a bona fide administrative or judicial appeal; and(b) if the person is a partnership, corporation, or other business association, provides the certification required by subsection (9)(a)(i) or (9)(a)(ii), as applicable, for any partners, officers, directors, owners of 10% or more of any class of voting stock, and business association members.Amended by Laws 2021, Ch. 152,Sec. 3, eff. 10/1/2021.Amended by Laws 2021, Ch. 324,Sec. 100, eff. 7/1/2021.Amended by Laws 2015, Ch. 399, Sec. 11, eff. 10/1/2015.En. Sec. 8, Ch. 252, L. 1971; amd. Sec. 4, Ch. 281, L. 1974; R.C.M. 1947, 50-1208; amd. Sec. 6, Ch. 588, L. 1979; amd. Sec. 13, Ch. 617, L. 1981; amd. Sec. 1, Ch. 489, L. 1983; amd. Sec. 1, Ch. 345, L. 1985; amd. Sec. 3, Ch. 453, L. 1985; amd. Sec. 2, Ch. 582, L. 1985; amd. Sec. 1, Ch. 311, L. 1987; amd. Sec. 4, Ch. 93, L. 1989; amd. Sec. 3, Ch. 347, L. 1989; amd. Sec. 4, Ch. 227, L. 1991; amd. Sec. 1, Ch. 403, L. 1991; amd. Sec. 4, Ch. 637, L. 1991; amd. Sec. 3, Ch. 598, L. 1993; amd. Sec. 390, Ch. 418, L. 1995; amd. Sec. 4, Ch. 507, L. 1999; amd. Sec. 5, Ch. 488, L. 2001; amd. Sec. 2, Ch. 365, L. 2003; amd. Sec. 3, Ch. 63, L. 2005; amd. Sec. 1, Ch. 145, L. 2011; amd. Sec. 3, Ch. 410, L. 2011.