The engineer shall proceed promptly to:
The engineer shall restrict the preliminary survey to the drainage area described in the petition, except that to secure an outlet the engineer may run levels necessary to determine the distance for the proper fall of the water. The preliminary survey must consider the impact of the proposed drainage project on the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1. The drainage authority may have other areas surveyed after:
The engineer may approve and include as a part of the report, a project of the United States relating to drainage or flood control that is within the proposed drainage project area, and may accept data, plats, plans, or information relating to the project furnished by United States engineers. The engineer does not need to make the preliminary survey if the material furnished by the United States is sufficient for the engineer to make the preliminary survey report.
The engineer shall report the proposed drainage project plan or recommend a different practical plan. The report must give sufficient information, in detail, to inform the drainage authority on issues related to feasibility, and show changes necessary to make the proposed plan practicable and feasible including extensions, laterals, and other work. If the engineer finds the proposed drainage project in the petition is feasible and complies with the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1, the engineer shall include in the preliminary survey report a preliminary plan of the drainage project showing the proposed ditches, tile, laterals, and other improvements, the outlet of the project, the watershed of the drainage project or system, and the property likely to be affected and its known owners. The plan must show:
Minn. Stat. § 103E.245
1990 c 391 art 5 s 37; 2014 c 164 s 5-7