This article applies to any quarry, including reclaimed and unreclaimed areas, if the quarry is more than one acre in size, the total excavated area including adjacent parcels under a common owner or operator is more than one acre in size or underground production blasting is proposed. [2007, c. 297, §8(AMD).]
This article does not apply to a quarry located wholly within the jurisdiction of the Maine Land Use Planning Commission. [1995, c. 700, §35(NEW); 2011, c. 682, §38(REV).]
This article does not apply to an excavation or grading preliminary to a construction project, unless intended to circumvent this article. [1995, c. 700, §35(NEW).]
A person with a valid permit for a quarry under article 6 must operate that quarry in compliance with the terms and conditions of that permit. Any modification of the permit must be in conformance with section 484. A person with a permit under article 6 may file a notice of intent to comply with this article. The permit issued under article 6 lapses as of the date a complete notice of intent is filed with the department. If the permittee chooses to substitute a notification pursuant to this article, all terms and conditions that applied to the permit issued pursuant to article 6 are incorporated into the notification approved pursuant to this article. [1995, c. 700, §35(NEW).]
38 M.R.S. § 490-X