No later than January 1, 1999, each investor-owned electric utility shall submit to the commission a plan to accomplish the divestiture required under this subsection. In an adjudicatory proceeding, the commission shall review the plans for consistency with this chapter. By July 1, 1999, the commission shall issue an order approving the plan or modifying the plan to make it consistent with the requirements of this chapter. An investor-owned electric utility shall divest its generation assets in accordance with the commission's order.
[1997, c. 558, §1(AMD).]
[1997, c. 316, §3(NEW).]
The commission by rule shall establish the procedure for granting extensions. Rules adopted under this subsection are routine technical rules pursuant to Title 5, chapter 375, subchapter II-A.
[1999, c. 577, §1(AMD).]
In the rules adopted under this subsection, the commission shall establish procedures to promote the maximum market value for these rights. Nothing in this subsection prohibits a utility from re-negotiating, buying out or buying down a contract with a qualifying facility in accordance with applicable laws. The commission shall adopt all rules required under this subsection. Rules adopted under this subsection are routine technical rules pursuant to Title 5, chapter 375, subchapter II-A.
[1999, c. 577, §2(AMD).]
[1997, c. 316, §3(NEW).]
[1997, c. 316, §3(NEW).]
[2003, c. 344, Pt. D, §24(AMD).]
Upon the issuance of a written finding by the commission under paragraph B, an electric utility is authorized to transfer those generation-asset-related rights, privileges and immunities identified in the written finding of the commission, provided that the electric utility complies with all other applicable requirements of law, including section 1101. The commission may issue a written finding under paragraph B in an order approving a divestiture of generation assets, pursuant to section 1101.
For purposes of this subsection, "generation-asset-related rights, privileges or immunities" means rights, privileges or immunities that constitute generation assets or that are necessary to the ownership or operation of generation assets, including water rights associated with hydro-electric facilities. For purposes of this subsection, the term "investor-owned electric utility" includes an affiliate of an investor-owned electric utility to the extent that the affiliate is transferring an asset that the affiliate is required to divest pursuant to this section.
Nothing in this subsection may be interpreted to permit the transfer of any rights, privileges or immunities that by law are expressly nontransferable or that are transferable only on condition, unless the condition is met. Nothing in this subsection may be interpreted as extinguishing or affecting any lawful rights, privileges or immunities that any person or entity or the public may have in any property held or transferred by an electric utility. Nothing in this section authorizes the sale or transfer of any right of eminent domain. Any right of eminent domain held by an investor-owned electric utility in relation to generation-asset-related rights, privileges or immunities terminates upon the divestiture of the generation-asset-related rights, privileges or immunities.
[1997, c. 710, §9(NEW).]
Any subsequent regulated activity relating to any resulting parcel is subject to all applicable regulatory reviews and approvals by a municipality or state agency. A municipality or state agency, in its review of any subsequent regulated activity relating to any resulting parcel, may consider the division of ownership accomplished pursuant to the exemption granted under this subsection and may, in accordance with applicable standards established by law, rule or ordinance, deny or condition its approval based on the cumulative effect of that division of ownership and the subsequent regulated activity, as though both were occurring at the same time.
For purposes of this subsection, "subsequent regulated activity" means any activity occurring after a division of ownership accomplished pursuant to the exemption granted under this subsection that is subject to regulatory review by a municipality or state agency, including any change of use, division of ownership or development. For purposes of this subsection, "resulting parcel" means a lot or parcel of real property resulting from a division of ownership accomplished pursuant to an exemption granted under this subsection.
[1999, c. 43, §1(NEW).]
The utility shall reform the contract so that the customer pays a total price for delivered electricity on an annual basis during the remaining term of the contract equal to the price contained in the contract. If the customer has exercised due diligence to obtain the lowest price from a competitive electricity provider for generation service for the remaining term of the contract, the utility shall reform the contract to provide a price for transmission and distribution services, stranded costs and all other applicable utility charges that is equal to the difference between the original contract price and the price for generation service obtained by the customer. If the customer has failed to exercise due diligence, the price must be equal to the difference between the original contract price and a reasonable market price for generation service for that customer.
If after good faith negotiations the contracting parties are unable to agree to a reformed contract, either party may petition the commission to resolve the dispute. The commission shall determine any unresolved issues and impose a reformed contract to preserve as nearly as possible the parties' benefits and burdens under the terms of the original contract. Prior to its final determination, the commission shall review updated information provided by the retail customer concerning the price of its generation service. The commission may not approve a retail contract with a price term longer than the expected duration of the retail customer's generation service contract. Changes to a contract reformed under this subsection take effect on March 1, 2000. A transmission and distribution utility shall ensure that any contract subject to this subsection has been reformed before that date.
[1999, c. 398, Pt. K, §1(NEW).]
For purposes of this subsection, "affiliate" means a person who has any direct or indirect ownership interest in, or is a direct or indirect subsidiary of a person who has any ownership interest in, the investor-owned transmission and distribution utility, but does not include a wholly owned or partially owned direct or indirect subsidiary of the investor-owned transmission and distribution utility.
Any affiliate generation or generation-related assets permitted under this subsection that do not have a commission-approved long-term contract or term sheet under this Title as of July 1, 2017 are ineligible to participate in a long-term contract under this Title.
Rules adopted pursuant to this subsection are major substantive rules as defined in Title 5, chapter 375, subchapter 2-A.
[2017, c. 287, §1(NEW).]
35-A M.R.S. § 3204