Ind. Code § 32-27-3-10

Current through P.L. 171-2024
Section 32-27-3-10 - Attorney's fees and costs to claimant

If a construction professional unreasonably:

(1) disputes a home owner's claim;
(2) fails to remedy or compromise and settle the claim;
(3) fails to repair the construction defect within a reasonable time, subject to the nature of the repair or some unforeseen event not caused by the construction professional; or
(4) fails to respond to a notice;

and the claimant commences an action governed by this chapter and prevails in the action, the court may award attorney's fees and costs to the claimant.

IC 32-27-3-10

As added by P.L. 134-2003, SEC.1.