Current through P.L. 171-2024
Section 13-18-3-12 - Adoption of rules waiving requirement of submission of plans The board shall adopt rules providing that whenever a person submits plans to a unit concerning the design or construction of:
(1) a sanitary sewer or public water main, if:(A) a professional engineer who is registered under IC 25-31 prepared the plans;(B) the unit provided for review of the plans by a qualified engineer and subsequently approved the plans; and(C) all other requirements specified in rules adopted by the board are met; or(2) a sanitary sewer extension for and within a subdivision, if:(A) a qualified professional surveyor who is registered under IC 25-21.5 prepared the plans;(B) the subdivision is being laid out or having been laid out by the professional surveyor subject to IC 25-21.5-7;(C) the unit provided for review of the plans by a qualified engineer and subsequently approved the plans; and(D) all other requirements specified in rules adopted by the board are met; the plans are not required to be submitted to any state agency for a permit, permission, or review, unless required by federal law.
Amended by P.L. 113-2014, SEC. 70, eff. 7/1/2014.Amended by P.L. 57-2013, SEC. 10, eff. 7/1/2013.Amended by P.L. 133-2012, SEC. 127, eff. 1/1/2013.As added by P.L. 104-1998, SEC.1. Amended by P.L. 241-1999, SEC.1.