220 ILCS 50/7.5

Current through Public Act 103-1052
Section 220 ILCS 50/7.5 - [Effective 1/1/2025] Exposed facility
(a) If any previously unmarked facility is exposed during excavation or demolition, emergency or nonemergency, the excavator responsible for the excavation or demolition operations shall immediately notify JULIE.
(b) At a minimum, the notice required under this Section shall provide:
(1) a reference to the original excavation or demolition notice, if one exists;
(2) the type of exposed facility, if known;
(3) the name of the affected underground utility facility owner or operator, if known; and
(4) the location of the exposed facility at the excavation or demolition site.

220 ILCS 50/7.5

Added by P.A. 103-0614,§ 5, eff. 1/1/2025.