In order to give the Department notice of the owner's or operator's intent to construct or modify an earthen livestock waste lagoon, the owner or operator shall register such lagoon with the Department during the preconstruction phase. Construction shall not begin until 30 days after submittal of a registration form by certified mail to the Department. When an informational meeting is requested by the county, construction shall not begin until after the informational meeting has been held.
Livestock waste lagoon registration forms shall be made available to producers at offices of the Department of Agriculture, Cooperative Extension Service, and Soil and Water Conservation Districts.
Registration information shall include the following:
The Department of Agriculture upon receipt of a livestock waste lagoon registration form shall review the form to determine that all required information has been provided. The person filing the registration shall be notified within 15 working days that the registration is complete or that clarification of information is needed. No later than 10 working days after receipt of the clarification information, the Department shall notify the owner or operator that the registration is complete.
The Department shall inspect an earthen livestock waste lagoon during preconstruction, construction, and post-construction. The Department shall require modifications when necessary to bring construction in compliance with the standards as set forth in subsection (a) of Section 15. The person making the inspection shall discuss with the owner, operator, or certified livestock manager an evaluation of the livestock waste lagoon construction and shall (i) provide on-site written recommendations to the owner, operator, or certified livestock manager of what modifications are necessary or (ii) inform the owner, operator, or certified livestock manager that the lagoon meets the standards set forth in subsection (a) of Section 15. On the day of the inspection, the person making the inspection shall give the owner, operator, or certified livestock manager a written report of his or her findings based on the inspection, together with an explanation of any remedial measures necessary to enable the lagoon to meet the standards set forth in subsection (a).
The person making any inspection shall comply with reasonable animal health protection procedures as requested by the owner, operator, or certified livestock manager.
Upon completion of the construction or modification, but prior to placing the lagoon in service, the owner or operator of the livestock waste lagoon shall certify on a form provided by the Department that the lagoon has been constructed or modified in accordance with the standards set forth in subsection (a) of Section 15 and that the information provided on the registration form is correct.
Within 10 business days of receipt of the certification of compliance, the Department shall inspect the lagoon site. The Department shall, within 5 business days of the date of inspection, send an official written notice by certified mail, return receipt requested, to the owner or operator of the facility indicating that all the requirements of this Section have been met or that deficiencies exist that must be corrected prior to the completion of the lagoon registration process and the placement of the lagoon into service. The owner or operator of the lagoon may proceed to place the lagoon in service after receipt of the Department's notice that all the requirements of this Section have been met.
The person making any inspection shall comply with animal health protection procedures as requested by the owner or operator.
Any earthen livestock waste lagoon in service prior to the effective date of the rules for implementation of this Act is not subject to registration but is only subject to the complaint procedure. However, any such livestock waste lagoon found impacting groundwater shall be required to be repaired, modified, or have procedures instituted so groundwater is not negatively impacted.
If an investigation reveals groundwater has been negatively impacted, the Department and Agency shall cooperate with the owner or operator of the affected livestock waste lagoon to provide a reasonable solution to protect the groundwater.
Nothing in this Section shall limit the Agency's authority under the Environmental Protection Act to investigate and respond to violations of the Environmental Protection Act or rules adopted under that Act.
Upon a change in ownership of a registered earthen livestock waste lagoon, the owner shall notify the Department of the change within 30 working days of the closing of the transaction.
Any earthen livestock waste lagoon subject to registration shall not begin operation until the owner or operator of the lagoon has met the requirements of this Act.
The owner or operator of any earthen livestock waste lagoon subject to registration that has not been registered or constructed in accordance with standards set forth in subsection (a) of Section 15 shall, upon being identified as such by the Department, be given written notice by the Department to register and certify the lagoon within 10 working days of receipt of the notice. The Department may inspect such lagoon and require compliance in accordance with subsections (a) and (b) of this Section. If the owner or operator of the livestock waste lagoon that is subject to registration fails to comply with the notice, the Department may issue a cease and desist order until such time as compliance is obtained with the requirements of this Act. Failure to construct the lagoon in accordance with the construction plan and Department recommendations is a business offense punishable by a fine of not more than $5,000.
510 ILCS 77/15