Va. Code § 62.1-44.15:26.1

Current with changes from the 2024 legislative session through ch. 845
Section 62.1-44.15:26.1 - Termination of Construction General Permit coverage
A. A VSMP authority shall recommend that the Department of Environmental Quality terminate coverage under a General Permit for Discharges of Stormwater from Construction Activities (Construction General Permit) within 60 days of receiving a complete notice of termination from the operator of the construction activity.
B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.
C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.

Va. Code § 62.1-44.15:26.1

2018, c. 630.
Added by Acts 2018 c. 630, § 1, eff. 7/1/2018.