Md. Code, PUC § 7-508

Current with changes from the 2024 Legislative Session
Section 7-508 - Transfer of assets
(a) An electric company may transfer any of its generation facilities or generation assets to an affiliate.
(b) The transfer of a generation facility or generation asset to an affiliate may not affect or restrict the Commission's determination of the value of a generation asset for purposes of transition costs or benefits under § 7-513(b) of this subtitle.
(c)
(1) This subsection is in effect until the later of the date when:
(i) all customers of the electric company are eligible for customer choice under § 7-510 of this subtitle; and
(ii) the amount of transition costs or benefits arising from the generation to be transferred has been finally determined by the Commission under § 7-513(a) through (c) of this subtitle.
(2) The Commission may review and approve the transfer for the sole purpose of determining:
(i) that the appropriate accounting has been followed;
(ii) that the transfer does not or would not result in an undue adverse effect on the proper functioning of a competitive electricity supply market; and
(iii) the appropriate transfer price and rate making treatment.
(3) The Commission shall act on the transfer of a generation facility or generation asset under this subsection within 180 days after the electric company files its proposed transfer application and any required supporting information.

Md. Code, PUC § 7-508