the obligee may require the contractor to strengthen any or all of the bonds or to furnish a new or additional bond or bonds within ten days. Thereupon, if so ordered by the obligee, all work on the contract shall cease unless such new or additional bond or bonds are furnished. If such bond or bonds are not furnished within such time, the obligee may terminate the contract and complete the same as the agent of and at the expense of the contractor and his or her sureties.
OCGA § 36-91-40