Cal. Pub. Contract Code § 10843

Current through the 2023 Legislative Session.
Section 10843 - Failure to prosecute work with diligence and force specified by contract

If the trustees deem that a contractor has failed to supply an adequate working force, or material of proper quality, or has failed in any other respect to prosecute the work with the diligence and force specified by the contract, the trustees may:

(a) After written notice of at least five days to the contractor, specifying the defaults to be remedied, provide any such labor or materials and deduct the cost from any money due or to become due to the contractor under the contract; or
(b) If the trustees consider that the failure is sufficient ground for such action, they may give written notice of at least five days to the contractor and the contractor's sureties, that if the defaults are not remedied the contractor's control over the work will be terminated.

Ca. Pub. Cont. Code § 10843

Added by Stats. 1984, Ch. 1128, Sec. 4.