1. A. B. is the plaintiff. |
2. C. D. is the owner of the structures hereafter referred to. |
3. (The labor hereafter referred to was done). (The materials hereafter referred to were furnished) by A. B. in or for the (erection) (alteration) (repair) of the structures pursuant to a contract made by A. B. with C. D. |
4. The amount claimed to be due to A. B. is five hundred dollars ($500.00) with interest on two hundred and fifty dollars ($250.00) from June 1, 1936 and on two hundred and fifty dollars ($250.00) from June 2, 1936 (for labor done on) (for lumber furnished for) and on account of said structures. A bill of particulars of the kind and amount of (labor done) (materials furnished) is annexed. |
5. The time when the (doing of the labor) (furnishing of the materials) was commenced was June 1, 1936. |
6. The time when the (doing of the labor) (furnishing of the materials) was finished was June 2, 1936. |
7. The structures are located on lots of land in Wilmington, New Castle County, Delaware, described as follows: |
Lot 1. Beginning at the intersection, etc. |
Lot 2. Beginning at the intersection, etc. |
8. (The labor was done) (The materials were furnished) on the credit of these structures. |
9. The amount of plaintiff's claim exceeds twenty-five dollars ($25.00), to wit, five hundred dollars ($500.00) with interest. Neither that sum nor any part thereof has been paid to plaintiff. |
10. The amount which plaintiff claims to be due him on each of the structures is as follows: |
On the structure on Lot 1, $250.00 with interest from May 1, 1936. |
On the structure on Lot 2, $250.00 with interest from June 2, 1936. |
______________________ |
Attorney for Plaintiff. |
(Jurat) |
Address: _______________ |
|
Bill of Particulars |
June 1, 1936, 5000 feet of pine boards 12 x 10 x 1, $250.00. |
June 2, 1936, 5000 feet of pine boards 12 x 10 x 1, $250.00. |