Wis. Admin. Code Public Service Commission PSC 113.0509

Current through October 28, 2024
Section PSC 113.0509 - Landowner easements
(1) When approaching a landowner in the course of negotiating new easements or renegotiating existing easements, the utility shall provide the landowner with materials approved or prepared by the commission describing the landowner's rights and options in the easement negotiation process. The landowner shall have, unless voluntarily waived by the landowner, a minimum period of five days to examine these materials before signing any new or revised easement agreement.
(2) High-voltage transmission line easements shall describe the interest transferred by specifying, in addition to the length and width of the right-of-way, the number, type and maximum height of all structures to be erected thereon, the minimum height of the transmission lines above the landscape and the number and maximum voltage of the lines to be constructed and operated thereon, as required by s. 182.017(7), Stats.

Wis. Admin. Code Public Service Commission PSC 113.0509

CR Register, July, 2000, No. 535, eff. 8-1-00.