Section R655-11-12E - Final Inspection

Before any dam can be placed in operation a final inspection of the project must be undertaken by the State Engineer and his written acceptance of the project received. The Emergency Action Plan, Standard Operating Plan, and Initial Filling Plan, if required, must be completed and approved before final acceptance and authorization for filling can be given. During rehabilitation of existing dams, at the discretion of the State Engineer, some reservoir storage may be allowed provided sufficient safety criteria are adopted. Record drawings of the project must be submitted within 60 days of the date of the final inspection. All record drawings submitted must be on a high quality reproducible medium or electronic format acceptable to the State Engineer. Record drawings shall reflect design changes made during construction, geological logs of the foundation excavation, and piezometer borings.