A final report consisting of a certification statement and expenditure report shall be submitted to the Department within 60 days of the completion of the project or expenditure, but in no event later than February 28 of the year following the year in which the grant was made. The recipient shall verify that funds were expended in accordance with the act and this chapter.
7 Pa. Code § 23.9