Or. Admin. Code § 345-027-0350

Current through Register Vol. 63, No. 10, October 1, 2024
Section 345-027-0350 - Changes Requiring an Amendment

Except for changes allowed under OAR 345-027-0353, an amendment to a site certificate is required to:

(1) Transfer ownership of the facility or the certificate holder as described in OAR 345-027-0400;
(2) Apply later-adopted laws as described in OAR 345-027-0390;
(3) Extend the construction beginning or completion deadline as described in OAR 345-027-0385;
(4) Design, construct, or operate a facility in a manner different from the description in the site certificate, if the proposed change:
(a) Could result in a significant adverse impact that the Council has not addressed in an earlier order and the impact affects a resource or interest protected by an applicable law or Council standard;
(b) Could impair the certificate holder's ability to comply with a site certificate condition; or
(c) Could require a new condition or a change to a condition in the site certificate.

Or. Admin. Code § 345-027-0350

EFSC 9-2019, temporary adopt filed 08/22/2019, effective 8/22/2019through 2/17/2020; EFSC 1-2020, adopt filed 01/28/2020, effective 1/28/2020

Statutory/Other Authority: ORS 469.470

Statutes/Other Implemented: ORS 469.405