Okla. Admin. Code § 165:35-25-24

Current through Vol. 42, No. 3, October 15, 2024
Section 165:35-25-24 - Utility performance scorecard
(a) Using the data submitted pursuant to OAC 165:35-25-20, PUD shall annually prepare a scorecard for each utility covering the following areas:
(1) SAIFI;
(2) SAIDI;
(3) MAIFI (to the extent that this measure is utilized);
(4) Vegetation management; and
(5) Worst performing circuits.
(b) The scorecard shall be prepared such that the performance of utilities of differing sizes and number of consumers can be directly compared.
(c) PUD's utility performance scorecards will be published annually not later than May 1.

Okla. Admin. Code § 165:35-25-24

Added at 21 Ok Reg 2091, eff 7-1-04
Amended by Oklahoma Register, Volume 31, Issue 24, September 2, 2014, eff. 9/12/2014
Amended by Oklahoma Register, Volume 36, Issue 21, July 15, 2019, eff. 7/25/2019