15A N.C. Admin. Code 18C.0309

Current through Register Vol. 39, No. 9, November 1, 2024
Section 18C .0309 - FINAL APPROVAL
(a) No construction, alteration, or expansion of a water system, subject to approval as described in Section .0300 of this Subchapter, shall be placed into final service or made available for human consumption until the applicant has complied fully with Section .0300 of this Subchapter and received Final Approval from the Department.
(b) Temporary approval may be granted by the Department for system alterations required to remedy an imminent hazard as determined by the Department.

15A N.C. Admin. Code 18C .0309

Authority G.S. 130A-315; 130A-317; P.L. 93-523;
Temporary Adoption Eff. October 1, 1999;
Eff. August 1, 2000;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. November 23, 2015.
Authority G.S. 130A-315; 130A-317; P.L. 93-523;
Temporary Adoption Eff. 10/1/1999;
Eff. 8/1/2000.