N.J. Admin. Code § 7:14A-22.14

Current through Register Vol. 56, No. 19, October 7, 2024
Section 7:14A-22.14 - Temporary wastewater hauling/diversion
(a) Wastewater hauling is the removal and transportation of a permitted quantity of wastewater from the headworks of a facility and prior to treatment, by a licensed waste hauler, from a treatment facility which is subject to a sewer ban, to a treatment facility which is not subject to a sewer ban. Wastewater diversion is the re-direction of a permitted quantity of wastewater flow from a collection or conveyance system to an alternate collection system not subject to a sewer connection ban.
1. Flow diversion may be accomplished by constructing various temporary gravity sewers or pumping stations or by modifying an existing collection system so that flows are re-directed to an alternative treatment works.
(b) The temporary use of wastewater hauling/diversion may be approved by the Department simultaneous or subsequent to the issuance of a stage II "dry/construct only" treatment works approval issued by the Department pursuant to 7:14A-22.9(a), for projects located in sewer ban areas, or if authorized by the Department through an administrative/judicial consent order executed by the applicant and the Department.

N.J. Admin. Code § 7:14A-22.14

Administrative correction.
See: 38 N.J.R. 5153(a).