N.J. Admin. Code § 5:23-12.9

Current through Register Vol. 56, No. 19, October 7, 2024
Section 5:23-12.9 - Certificate of compliance requirements
(a) A device shall be granted a certificate of compliance by the construction official for the time period specified based upon 5:23-12.3. No device shall be operated unless a valid certificate of compliance has been issued except for the initial period after work under a permit has been completed as per (f) below. Any violation shall be corrected before a new certificate of compliance may be issued.
(b) A temporary certificate of compliance may be issued by the construction official for a device in order to keep the device in operation on which work, as a result of violations, is being diligently performed, if the elevator subcode official finds that no hazard to the public is thereby created. A temporary certificate of compliance may be issued for no longer than the inspection cycle.
(c) The elevator subcode official shall provide written notice to the construction official whenever a temporary certificate of compliance or certificate of compliance is granted by the construction official.
(d) No certificate of compliance shall be issued for any elevator device in use on or before July 1, 1992 that is subject to these rules and is not registered with the Department in accordance with 5:23-12.4, except elevator devices in structures classified as Group R-3, R-4, or R-5 shall be exempt from registration. Elevator devices wholly within dwelling units in structures of Group R-2 and not accessible to the general public shall also be exempt.
(e) No certificate of compliance or temporary certificate of compliance shall be issued for any elevator device, as required by this section, which has been approved to operate during the initial period, after a permit, in accordance with (f) below if the device has not been registered pursuant to this subchapter by its first cyclical inspection, even if a certificate of occupancy, temporary certificate of occupancy, or certificate of approval has been issued.
(f) Except as otherwise provided in (e) above, a new device or an existing device which has had work done under a permit shall be issued a certificate of compliance upon the first cyclical inspection based on the following:
1. A device has been approved following the inspection and witnessing of an acceptance test, as required by 5:23-12.2, by the application of an Inspection Sticker Approval for Elevator and a recommendation by the elevator subcode official on an Elevator Subcode Technical Section form for a certificate of occupancy or approval, as the case may be.
i. The date of the approval shall begin the cycle of inspections and tests for new devices in a new building and for new devices in an existing building which did not have elevator devices previously.
ii. The date of the approval of an existing device in an existing building shall not change the device's existing cycle of inspections and tests. The cycle shall remain consistent with the inspection cycle in the building, except the device shall not be subject to the five year test before it is due as long as the acceptance test performed under the permit was a full five year test.
2. A device has been approved following the inspection process, as required for minor work by N.J.A.C. 5:23-2.17A(d)2 and 12.2, by the application of an Inspection Sticker of Approval for Elevator and a recommendation by the elevator subcode official on an Elevator Subcode Technical Section form for a certificate of approval.
i. The device may operate under the approval given under the permit until the next cyclical inspection, as determined by the inspection cycle of the building, and then shall be subject to the applicable routine or periodic inspection the same as all other elevator devices in the building.

N.J. Admin. Code § 5:23-12.9

Adopted by 49 N.J.R. 1848(a), effective 7/3/2017