Minn. R. agency 167, ch. 7001, NPDES PERMITS, pt. 7001.1040

Current through Register Vol. 49, No. 20, November 12, 2024
Part 7001.1040 - APPLICATION DEADLINE FOR NEW PERMITS
A. If a person proposes to construct a new facility or engage in a new activity for which a permit is required, the person shall submit a written permit application at least 180 days before the planned date of the commencement of facility construction or of the planned date of the commencement of the activity, whichever occurs first.
B. Persons proposing activities that require a general construction storm water permit under chapter 7090 must submit an application provided by the agency prior to initiation of construction.

Minn. R. agency 167, ch. 7001, NPDES PERMITS, pt. 7001.1040

8 SR 2277; 19 SR 1901; 30 SR 125

Statutory Authority: MS s 115.03; 116.07