Mich. Admin. Code R. 323.1709

Current through Vol. 24-18, October 15, 2024
Section R. 323.1709 - Earth change requirements: time; sediment removal; design, installation, and removal of temporary or permanent control measures

Rule 1709.

(1) A person shall design, construct, and complete an earth change in a manner that limits the exposed area of any disturbed land for the shortest possible period of time as determined by the county or local enforcing agency.
(2) A person shall remove sediment caused by accelerated soil erosion from runoff water before it leaves the site of the earth change.
(3) A person shall design a temporary or permanent control measure that is designed and constructed for the conveyance of water around, through, or from the earth change area to limit the water flow to a nonerosive velocity.
(4) A person shall install temporary soil erosion and sedimentation control measures before or upon commencement of the earth change activity and shall maintain the measures on a daily basis. A person shall remove temporary soil erosion and sedimentation control measures after permanent soil erosion measures are in place and the area is stabilized. A person shall stabilize the area with permanent soil erosion control measures under approved standards and specifications as prescribed by R 323.1710.
(5) A person shall complete permanent soil erosion control measures for all slopes, channels, ditches, or any disturbed land area within 5 calendar days after final grading or the final earth change has been completed. If it is not possible to permanently stabilize a disturbed area after an earth change has been completed or if significant earth change activity ceases, then a person shall maintain temporary soil erosion and sedimentation control measures until permanent soil erosion control measures are in place and the area is stabilized.

Mich. Admin. Code R. 323.1709

1979 AC; 1998 AACS