Md. Code Regs. 26.20.22.04

Current through Register Vol. 51, No. 22, November 1, 2024
Section 26.20.22.04 - Public Notice of Changes to Blasting Schedules
A. Before blasting in areas or at times not in a previous schedule, the permittee shall publish and distribute a revised blasting schedule, at least 10 days but not more than 30 days before blasting. Information on requesting a pre-blast survey need not be repeated in a change notice.
B. If there is a substantial pattern of non-adherence to the published blasting schedule as evidenced by the absence of blasting during a scheduled period, the Bureau may require that the permittee submit to the Bureau and republish a revised blasting schedule.

Md. Code Regs. 26.20.22.04

Regulations .04 were previously codified as COMAR 08.13.09.25 a A_H, respectively. Recodification occurred in April, 1993. For a history of these regulations before April, 1993, see "Administrative History of COMAR 08.13.09 before April, 1993" which follows COMAR 26.20.01.