Iowa Admin. Code r. 761-115.29

Current through Register Vol. 47, No. 6, October 2, 2024
Rule 761-115.29 - Notice of work
(1)Notice of receipt of permits and approvals. The utility owner shall notify the department within 14 calendar days after the utility owner has received all required permits and approvals from government agencies and railroad companies.
(2)Notice to utility owner to begin work.
a. The department shall send a notice to proceed to the utility owner not less than 3 0 calendar days before the utility owner is required to begin the work provided for in its work plan.
b. If the utility owner's work plan is dependent upon work by the highway contractor, the contractor shall provide the department and the utility owner a good faith notice 14 calendar days before the contractor's work is expected to be complete and ready for the utility owner to begin its work. The highway contractor shall follow up with a confirmation notice to the department and the utility owner not less than three working days before the contractor's work will be complete and ready for the utility owner to begin its work.
(3)Notice to department of commencement and completion of work. The utility owner shall give the department 48 hours' prior notice, excluding weekends and holidays, of its intent to start utility adjustment work within the project limits. The utility owner shall also notify the department immediately upon completion of the work.

Iowa Admin. Code r. 761-115.29