Ill. Admin. Code tit. 44 § 6.955

Current through Register Vol. 48, No. 45, November 8, 2024
Section 6.955 - Interim Agreements

Prior to or in connection with the negotiation of the public private agreement, the Department may enter into one or more interim agreements with the selected offeror or other vendors if the Department determines in writing that it is in the public interest to do so. (Section 30 of the Act)

a) The interim agreement may not authorize the contractor to perform construction work prior to the execution of the public private agreement. (Section 30(b) of the Act)
b) The interim agreement may include any or all of the provisions set forth in Section 30(c) of the Act. (Section 30(c) of the Act)

Ill. Admin. Code tit. 44, § 6.955

Added at 37 Ill. Reg. 15878, effective September 27, 2013