Section 13-277-5 - Interim protection measures

Interim protection measures shall protect the significant historic property and its buffer zone during construction activities. Interim measures may include:

(1) Flagging the perimeter of the buffer zone;
(2) Erecting barriers (such as plastic fencing) along the buffer zone;
(3) Placing avoidance instructions on construction plans and specifications;
(4) On-site, pre-construction briefing of the hired construction firm; and
(5) Having an archaeological monitor on-site during ground alteration activities.

Haw. Code R. § 13-277-5

[Eff DEC 11 2003] (Auth: HRS § 6E-3) (Imp: HRS §§ 6E-3, 6E-7, 6E-8, 6E-42)