Rule 110-5-1-.12 - Close-out and Reporting Requirements

Recipients of Efficiency Assessment and Consolidation Planning grants will be required to submit information as specified in a contract with the Department before receiving final payment of grant monies. Recipients of Consolidation Implementation grants will be required to report information to the Department on consolidation efforts and results, as requested by the Department. The Future Communities Commission will be required to Submit its final report and implementation plan and any legislation resulting from its recommendations.

Ga. Comp. R. & Regs. R. 110-5-1-.12

O.C.G.A Secs. 36-86-4, 50-8-8.

Original Grant description entitled "Close-out and Reporting Requirements" received August 17, 1995.