CIACOH | = | Total estimated work order job cost of installing the facilities | - | Four years expected incremental base energy revenue | - | Four years expected incremental base demand revenue, if applicable |
CIACUG | = | CIACOH | + | Estimated difference between cost of providing the service underground and overhead |
Fla. Admin. Code Ann. R. 25-6.064
Rulemaking Authority 366.05(1), 350.127(2) FS. Law Implemented 366.03, 366.05(1), 366.06(1) FS.
New 7-29-69, Amended 7-2-85, Formerly 25-6.64, Amended 2-1-07, 12-10-20.