4 Colo. Code Regs. § 723-3-3928

Current through Register Vol. 47, No. 20, October 25, 2024
Section 4 CCR 723-3-3928 - Qualifying Facility to File Generation Schedule

A qualifying facility shall provide a utility with a proposed schedule of generation prior to interconnection. The schedule may be used by the utility to coordinate normal maintenance of its distribution facilities, to coordinate its bulk power supplies, or to coordinate regular operations for the safety of maintenance personnel.

4 CCR 723-3-3928

38 CR 17, September 10, 2015, effective 9/30/2015
39 CR 06, March 25, 2016, effective 4/14/2016
39 CR 08, April 25, 2016, effective 5/15/2016
40 CR 22, November 25, 2017, effective 12/15/2017
42 CR 03, February 10, 2019, effective 3/2/2019
42 CR 07, April 10, 2019, effective 4/30/2019
42 CR 09, May 10, 2019, effective 5/30/2019
43 CR 08, April 25, 2020, effective 5/15/2020
43 CR 12, June 25, 2020, effective 7/15/2020
43 CR 20, October 25, 2020, effective 11/14/2020
44 CR 13, July 10, 2021, effective 7/30/2021
44 CR 24, December 25, 2021, effective 1/14/2022
45 CR 18, September 25, 2022, effective 10/15/2022
46 CR 02, January 25, 2023, effective 2/14/2023