Current through Register Vol. 47, No. 20, October 25, 2024
Section 4 CCR 723-3-3601 - Overview and PurposeThe purpose of these rules is to establish a process to determine the need for additional electric resources by electric utilities subject to the Commission's jurisdiction and to develop cost-effective resource portfolios to meet such need reliably. It is the policy of the state of Colorado that a primary goal of electric utility resource planning is to minimize the net present value of revenue requirements. It is also the policy of the state of Colorado that the Commission gives the fullest possible consideration to the cost-effective implementation of new clean energy and energy-efficient technologies.
38 CR 17, September 10, 2015, effective 9/30/201539 CR 06, March 25, 2016, effective 4/14/201639 CR 08, April 25, 2016, effective 5/15/201640 CR 22, November 25, 2017, effective 12/15/201742 CR 03, February 10, 2019, effective 3/2/201942 CR 07, April 10, 2019, effective 4/30/201942 CR 09, May 10, 2019, effective 5/30/201943 CR 08, April 25, 2020, effective 5/15/202043 CR 12, June 25, 2020, effective 7/15/202043 CR 20, October 25, 2020, effective 11/14/202044 CR 13, July 10, 2021, effective 7/30/202144 CR 24, December 25, 2021, effective 1/14/202245 CR 18, September 25, 2022, effective 10/15/202246 CR 02, January 25, 2023, effective 2/14/2023