43 C.F.R. § 404.37

Current through August 31, 2024
Section 404.37 - How will Reclamation determine the appropriate non-Federal share of construction costs?

Reclamation will determine the appropriate non-Federal share of construction costs in the process of developing the feasibility report. The non-Federal cost-share will be:

(a) At least 25 percent of the total construction costs; and
(b) An additional amount based on your capability to pay, as appropriate, to be determined by Reclamation based on the factors in § 404.39 .

43 C.F.R. §404.37