Current through October 31, 2024
Section 495.342 - Annual HIT IAPD requirementsEach State is required to submit the HIT IAPD Updates 12 months from the date of the last CMS approved HIT IAPD and must contain the following:
(a) A reference to the approved HIT PAPD/IAPD and all approved changes.(b) A project activity status which reports the status of the past year's major project tasks and milestones, addressing the degree of completion and tasks/milestones remaining to be completed and discusses past and anticipated problems or delays in meeting target dates in the approved HIT technology PAPD/IAPD and approved changes to it.(c) A report of all project deliverables completed in the past year and degree of completion for unfinished products.(d) A project activity schedule for the remainder of the project.(e) A project expenditure status which consists of a detailed accounting of all expenditures for project development over the past year and an explanation of the differences between projected expenses in the approved HIT PAPD/IAPD and actual expenditures for the past year.(f) A report of any approved or anticipated changes to the allocation basis in the advance planning document's approved cost methodology. 75 FR 44565 , July 28, 2010, as amended at 77 FR 54162 , Sept. 4, 2012