18 C.F.R. § 4.101

Current through October 31, 2024
Section 4.101 - Applicability

This subpart provides procedures for exemption on a case-specific basis from all or part of Part I of the Federal Power Act (Act), including licensing, for small hydroelectric power projects as defined in § 4.30(b)(31) .

18 C.F.R. §4.101

Order 202, 47 FR 4243, Jan. 29, 1982, as amended by Order 413, 50 FR 11687, Mar. 25, 1985; Order 482, 52 FR 39630, Oct. 23, 1987; Order 2002, 68 FR 51121 , Aug. 25, 2003; Order 800, 79 FR 59111 , Oct. 1, 2014

Energy Security Act of 1980, Pub. L. 96-294 , 94 Stat. 611; Federal Power Act, as amended (16 U.S.C. 792-828c ) ; Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2601-2645 ) ; and the Department of Energy Organization Act (42 U.S.C. 7101-7352 ) ; E.O. 12009, 3 CFR 142 (1978)