Cal. Code Regs. tit. 20 § 16.6

Current through Register 2024 Notice Reg. No. 45, November 8, 2024
Section 16.6 - (Rule 16.6) Extension of Time to Comply

Requests for extension of time to comply with a Commission decision or order may be made by letter or e-mail to the Executive Director, with a copy served at the same time on all parties to the proceeding and on the Administrative Law Judge Division (by letter to the Chief Administrative Law Judge, or by e-mail to aljextensionrequests@cpuc.ca.gov). A copy of the certificate of service must be attached to the letter or e-mail. The e-mail, the letter, or a facsimile of the letter, must be received by the Executive Director at least five business days before the existing date for compliance. If the Executive Director grants the extension, the party requesting the extension must promptly inform all parties to the proceeding of the extension and must state in the opening paragraph of the document that the Executive Director has authorized the extension.

Cal. Code Regs. Tit. 20, § 16.6

1. New section filed 9-13-2006; operative 9-13-2006 pursuant to Government Code section 11351(a) (Register 2006, No. 37).
2. Amendment filed 5-9-2011; operative 6-8-2011. Submitted to OAL for limited review pursuant to Government Code section 11351 and Public Utilities Code section 311(h) (Register 2011, No. 19).
3. Amendment filed 1-8-2014; operative 4-1-2014. Submitted to OAL for limited review pursuant to Government Code section 11351 and Public Utilities Code section 311(h) (Register 2014, No. 2).

Note: Authority cited: Section 1701, Public Utilities Code; and Section 2, Article XII, California Constitution. Reference: Section 1708, Public Utilities Code.

1. New section filed 9-13-2006; operative 9-13-2006 pursuant to Government Code section 11351(a) (Register 2006, No. 37).
2. Amendment filed 5-9-2011; operative 6-8-2011. Submitted to OAL for limited review pursuant to Government Code section 11351 and Public Utilities Code section 311(h) (Register 2011, No. 19).
3. Amendment filed 1-8-2014; operative 4-1-2014. Submitted to OAL for limited review pursuant to Government Code section 11351 and Public Utilities Code section 311(h) (Register 2014, No. 2).