Cal. Code Regs. tit. 20 § 11.6

Current through Register 2024 Notice Reg. No. 43, October 25, 2024
Section 11.6 - (Rule 11.6) Motion for Extension of Time

Motions for extension of time limits established in these rules or in a ruling of an Administrative Law Judge or Commissioner may be made orally, by e-mail, or by letter to the Administrative Law Judge. If other parties to the proceeding are affected by the extension, the party requesting the extension must first make a good-faith effort to ask such parties to agree to the extension. The party requesting the extension must report the results of this effort when it makes its request. If the extension is granted, the party requesting the extension shall notify all other parties to the proceeding of the extension, unless the grant of the extension is by oral ruling delivered on the record of the proceeding. If the extension is in regard to the time to file a document, the opening paragraph of the document shall indicate that the Administrative Law Judge has granted the extension. No extensions will be granted of time requirements established by statute, unless the statute permits extension or waiver of the requirement.

Cal. Code Regs. Tit. 20, § 11.6

1. Renumbering of former section 48 to new section 11.6, including amendment of section heading and section filed 9-13-2006; operative 9-13-2006 pursuant to Government Code section 11351(a) (Register 2006, No. 37).
2. Amendment filed 6-4-2009; operative 7-4-2009 (Register 2009, No. 23). Submitted to OAL for limited review pursuant to Government Code section 11351 and Public Utilities Code section 311(h).

Note: Authority cited: Section 1701, Public Utilities Code; and Section 2, Article XII, California Constitution. Reference: Section 1701, Public Utilities Code.

1. Renumbering of former section 48 to new section 11.6, including amendment of section heading and section filed 9-13-2006; operative 9-13-2006 pursuant to Government Code section 11351(a) (Register 2006, No. 37).
2. Amendment filed 6-4-2009; operative 7-4-2009 (Register 2009, No. 23). Submitted to OAL for limited review pursuant to Government Code section 11351 and Public Utilities Code section 311(h).