Production Facility Type | Unit Cost |
Per tank (>10,001 bbl) | $186,723 |
Per tank (5,001-10,000 bbl) | $127,510 |
Per tank (2,500-5,000 bbl) | $76,313 |
Per tank (<2,499 bbl) | $22,961 |
Per vessel, including each separator, heater-treater, free-water knockout, boiler, and steam-generator | $14,382 |
Per linear foot of above-ground pipelines | $26 |
Per linear foot of buried pipelines | $9 |
Per short ton of electrical vaults and equipment | $450 |
Per cubic foot of asphalt and concrete | $12 |
Per pump or pumping unit | $5,149 |
Per compressor | $5,149 |
Per square foot of buildings on site | $33 |
Characteristics | Points |
The production facility is environmentally sensitive or is located in a sensitive area or urban area, as defined in Section 1760 | 10 |
There has been a reportable spill or leak at the production facility | 10 |
The production facility is located on land that has or had a freshwater aquifer underneath | 5 |
The production facility is located in an area of known geologic hazards including subsidence, landslides, or seismicity | 5 |
There are surface obstacles or other impediments preventing access to the production facility, including but not limited to buildings or structures, surface-use activities, irrigation systems, roads, terrain, or restricted access | 5 |
The production facility is greater than 50 years old | 5 |
There is an unresolved notice of violation at the production facility | 5 |
Any other conditions about the production facility that indicate it could potentially pose a threat to life, health, property, or natural resources | 10 |
Maximum Potential Aggregated Risk Score | 55 |
Cal. Code Regs. Tit. 14, § 1753.2.1
Note: Authority cited: Sections 3013 and 3205.7, Public Resources Code. Reference: Sections 3011, 3106 and 3205.7, Public Resources Code.