Ariz. Admin. Code § 2-7-604

Current through Register Vol. 30, No. 44, November 1, 2024
Section R2-7-604 - Contract Change Orders and Amendments
A. The agency chief procurement officer may extend or authorize options in a contract provided the price of the extension or option was evaluated under the contractor's original offer.
B. Any contract change order or amendment or aggregate change orders or amendments of a contract not covered under sub-section (A) that exceeds 25% of the original contract amount may be executed only if the state procurement administrator or, in the case of construction on state property, the Assistant Director of General Services, determines in writing that the change order or amendment is advantageous to the state and the price is determined fair and reasonable pursuant to R2-7-702.
C. The agency chief procurement officer may, in situations in which time or economic consideration preclude resolicitation, negotiate a reduction to the contract, including scope, price, and contract requirements under A.R.S. § 41-2537.

Ariz. Admin. Code § R2-7-604

New Section made by final rulemaking at 12 A.A.R. 508, effective April 8, 2006 (Supp. 06-1). Amended by final rulemaking at 20 A.A.R. 3510, effective 2/2/2015.