Section 3 AAC 52.670 - Other requirements

A participating electric utility shall

(1) install and maintain adequate meters to measure kilowatt-hours of generation, fuel consumption, and energy consumption by all ratepayers as prescribed by 3 AAC 107.200;
(2) make reasonable efforts to minimize administrative, operating, and overhead costs, including use of the best available technology consistent with sound utility management practices;
(3) cooperate with appropriate state agencies to implement cost-effective energy conservation measures and to plan for and implement feasible alternatives to diesel generation; and
(4) file a monthly report with the Alaska Energy Authority in accordance with the requirements of AS 42.45.110(h)(1) and 42.45.170(a)(2).