From Casetext: Smarter Legal Research

Utica Mut. Ins. Co. v. Clearwater Ins. Co.

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK
Jul 14, 2016
6:13-cv-1178 (GLS/TWD) (N.D.N.Y. Jul. 14, 2016)

Opinion

6:13-cv-1178 (GLS/TWD)

07-14-2016

UTICA MUTUAL INSURANCE COMPANY, Plaintiff, v. CLEARWATER INSURANCE COMPANY, Defendant.


SUMMARY ORDER

Plaintiff Utica Mutual Insurance Company commenced this diversity action against defendant Clearwater Insurance Company, alleging breach of contract claims and seeking declaratory relief and damages. (See generally Compl., Dkt. No. 1.) Clearwater counterclaimed for breach of contract and sought damages to recoup payment already provided to Utica. (Dkt. No. 17 ¶¶ 66-70.) On January 20, 2016, the court granted Utica partial summary judgment, denied Clearwater's cross motion for summary judgment on its counterclaim, and dismissed that counterclaim. (Dkt. No. 106.) Accordingly, the court awarded Utica approximately $5.7 million in principal damages.

The calculation of principal damages is ongoing because Clearwater continues not to pay Utica's billings. (Dkt. No. 113 ¶ 1; Dkt. No. 122 at 2 n.1.) At the request of the court, the parties calculated the principal balance as of July 11, 2016 at $5,947,094.74. (Dkt. No. 129.)

Following entry of partial judgment, (Dkt. No. 108), the parties filed cross notices of appeal to the Second Circuit. (Dkt. Nos. 115, 117.) Still pending, however, were issues over the calculation of damages and prejudgment interest raised by the court sua sponte. (Dkt. No. 106 at 25; Dkt. Nos. 112, 114, 119-22.) On June 16, 2016, the court conducted a status conference to discuss outstanding damages issues. (Dkt. No. 126.) At the conclusion of the conference, the parties agreed to discuss settlement regarding prejudgment interest, (id. at 22-23), however, they were unable to resolve their disputes, (Dkt. No. 124). As a result, the court has been left to resolve the outstanding issues and does so as set forth below.

Because premature appeals from a nonfinal order do not divest a district court of jurisdiction, see Dudley ex rel. Estate of Patton v. Penn-Am. Ins. Co., 313 F.3d 662, 664 (2d Cir. 2002); Cooper v. Salomon Bros. Inc., 1 F.3d 82, 84 (2d Cir. 1993); see also 28 U.S.C. § 1291, the court may evaluate the issues of damages.

Under N.Y. C.P.L.R. 5001(a), "[i]nterest shall be recoverable upon a sum awarded because of a breach of performance of a contract." The statutory interest rate, which is not disputed by the parties, is nine percent per annum. See N.Y. C.P.L.R. 5004. When presented with multiple contract breaches at various times, the court has the discretion to award interest under one of two calculations. See N.Y. C.P.L.R. 5001(b); see also Mogil v. Building Essentials, Inc., 129 A.D.3d 1378, 1380 (3d Dep't 2015); Pac. Westeel, Inc. v. D & R Installation, No. 01Civ.0293, 2003 WL 22359512, at *3 (S.D.N.Y. Oct. 17, 2003) (applying New York law). Under the first calculation, "interest shall be computed upon each item from the date it was incurred." Id. Alternatively, under the second calculation, the court may opt to award interest "upon all of the damages from a single reasonable intermediate date." N.Y. C.P.L.R. 5001(b); Pac. Westeel, Inc., 2003 WL 22359512, at *3 (("When precision isn't practicable, [N.Y. C.P.L.R. 5001(b)] allows the fact-trier to select a single reasonable intermediate date from which the interest may be computed on all of the items together") (internal quotation marks and citations omitted)). "'[W]here damages are incurred at various times after the cause of action accrues, [N.Y. C.P.L.R.] 5001 grants courts wide discretion in determining a reasonable date from which to award pre-judgment interest.'" Wechsler v. Hunt Health Sys., Ltd., 330 F. Supp. 2d 383, 435 (S.D.N.Y. 2004) (quoting Conway v. Icahn & Co., 16 F.3d 504, 512 (2d Cir. 1994)); see Koylum, Inc. v. Peksen Realty Corp., 357 F. Supp. 2d 593, 596 (E.D.N.Y. 2005).

In a case premised on diversity jurisdiction, state law governs the award of prejudgment interest as a matter of substantive law. See Baker v. Dorfman, 239 F.3d 415, 425 (2d Cir. 2000). Here, as noted in the court's earlier opinions, New York law governs. (Dkt. No. 54 at 6 n.3; Dkt. No. 106 at 10 n.4.)

As recognized by the parties, this case presents a difficult prejudgment interest calculation. There are nearly forty breaches, and the parties dispute the length of the billing grace period, whether interest is owed on Clearwater's pre-litigation partial payments, and how to account for Utica's September 2015 credit. (See generally Dkt. Nos. 119-22.) After considering the complexities presented under the first calculation, the court opts to use the second calculation and select a single reasonable intermediate date. Accordingly, prejudgment interest shall run from the midpoint between ninety days after the oldest unpaid billing of November 2, 2012 and ninety days after the most recent unpaid billing of March 22, 2016 through July 14, 2016, the date of this order. Ninety days after the dates of the billings are January 31, 2013 and June 20, 2016, respectively. The midpoint between these two dates is October 11, 2014. Interest, on the principal amount of $5,947,094.74 from October 11, 2014 to July 14, 2016 at the nine percent rate, amounts to $941,433.24.

The parties agree that the most recent billing is dated March 22, 2016. (Dkt. No. 129.)

This calculation is consistent with other cases in which courts are tasked to determine a single reasonable intermediate date, see Oy Saimaa Lines Logistics Ltd. v. Mozaica-New York, Inc., 193 F.R.D. 87, 91 (E.D.N.Y. 2000) (collecting cases), without overly burdening the court to engage in a complicated formula after providing the parties with the opportunity settle this issue amongst themselves.

Accordingly, it is hereby

ORDERED that judgment in the amount of $5,947,094.74 plus prejudgment interest in the amount of $941,433.24 be entered in favor of Utica; and it is further

ORDERED that Clearwater is obligated to pay all future billings that are consistent with past billings under Reinsurance Contract No. N 21163, within ninety (90) days of the date of each such billing, up to the total amount of $5,000,000 under that Reinsurance Contract (inclusive of amounts that Reinsurance Contract that comprise part of the principal balance of $5,947,094.74); and it is further

ORDERED that Clearwater is obligated to pay all future billings that are consistent with past billings under Reinsurance Contract Nos. V-1522, HC-80-0098, and HC-81-0098, within ninety (90) days of the date of each such billing; and it is further

ORDERED that the Clerk shall provide a copy of the Summary Order to the parties.

IT IS SO ORDERED.

July 14, 2016
Albany, New York

/s/_________

Gary L. Sharpe

U.S. District Judge


Summaries of

Utica Mut. Ins. Co. v. Clearwater Ins. Co.

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK
Jul 14, 2016
6:13-cv-1178 (GLS/TWD) (N.D.N.Y. Jul. 14, 2016)
Case details for

Utica Mut. Ins. Co. v. Clearwater Ins. Co.

Case Details

Full title:UTICA MUTUAL INSURANCE COMPANY, Plaintiff, v. CLEARWATER INSURANCE…

Court:UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK

Date published: Jul 14, 2016

Citations

6:13-cv-1178 (GLS/TWD) (N.D.N.Y. Jul. 14, 2016)

Citing Cases

Utica Mut. Ins. Co. v. Clearwater Ins. Co.

The background facts are not in dispute. See Utica Mut. Ins. Co. v. Clearwater Ins. Co. (Utica I ), No.…