Greystone Bldg. & Dev. Corp. v. Makro Gen. Contractors, Inc.

Appellate Division of the Supreme Court of the State of New York
Mar 10, 2020
181 A.D.3d 468 (N.Y. App. Div. 2020)

Opinion

11235 Index 450271/16

03-10-2020

GREYSTONE BUILDING & DEVELOPMENT CORP., Plaintiff–Appellant, v. MAKRO GENERAL CONTRACTORS, INC., et al., Defendants–Respondents, The New York City Transit Authority, Defendant.

Flanagan Law, PLLC, New York (Richard J. Flanagan of counsel), for appellant. Peckar & Abramson, P.C., New York (Howard M. Rosen of counsel), for respondents.


Flanagan Law, PLLC, New York (Richard J. Flanagan of counsel), for appellant.

Peckar & Abramson, P.C., New York (Howard M. Rosen of counsel), for respondents.

Gische, J.P., Webber, Gesmer, Kern, JJ.

Order, Supreme Court, New York County (David Benjamin Cohen, J.), entered on or about December 10, 2018, which denied plaintiff's motion for summary judgment, and granted defendants Makro General Contractors, Inc. and Hercules Argyriou's motion to dismiss the complaint as against them, unanimously modified, on the law, to deny defendants' motion, and otherwise affirmed, without costs.

Summary judgment in plaintiff's favor on its claim for payment for work performed is precluded by issues of fact as to the portion of the contract that was performed and the portion that was deleted (see e.g. F. Garofalo Elec. Co. v. New York Univ. , 300 A.D.2d 186, 189, 754 N.Y.S.2d 227 [1st Dept. 2002] ; Sea Crest Constr. Corp. v. City of New York , 286 A.D.2d 652, 730 N.Y.S.2d 332 [1st Dept. 2001] ).

Defendants are not entitled to dismissal of the complaint on the ground that the action was commenced outside the one-year period of limitations contained in the subcontract between defendant Makro and plaintiff for claims arising out of the subcontract. While there is nothing inherently unreasonable about the one-year limitations period, it is unenforceable under the circumstances of this case (see AWI Sec. & Investigations, Inc. v. Whitestone Constr. Corp. , 164 A.D.3d 43, 47, 82 N.Y.S.3d 14 [1st Dept. 2018] ; D & S Restoration, Inc. v. Wenger Constr. Co., Inc. , 160 A.D.3d 924, 75 N.Y.S.3d 505 [2d Dept. 2018] ). After work commenced, a certain portion of the subcontracted work became impracticable, and deletions and change orders were made to Makro's prime contract with defendant New York City Transit Authority (NYCTA) and, by extension, the subcontract. Although, according to plaintiff's principal (additional defendant on counterclaim Theodore Melittas), plaintiff's work was substantially completed in September of 2013, negotiations among NYCTA, Makro and plaintiff over the value of the credit for the deleted work proceeded until September of 2015. However, under the subcontract, plaintiff was not entitled to final payment until NYCTA paid Makro. Thus, the one-year limitation period had run before the final negotiations were complete, i.e., before NYCTA would have paid Makro (see Executive Plaza, LLC v. Peerless Ins. Co. , 22 N.Y.3d 511, 518, 982 N.Y.S.2d 826, 5 N.E.3d 989 [2014] ["A ‘limitation period’ that expires before suit can be brought is not really a limitation period at all, but simply a nullification of the claim"] ).


Summaries of

Greystone Bldg. & Dev. Corp. v. Makro Gen. Contractors, Inc.

Appellate Division of the Supreme Court of the State of New York
Mar 10, 2020
181 A.D.3d 468 (N.Y. App. Div. 2020)
Case details for

Greystone Bldg. & Dev. Corp. v. Makro Gen. Contractors, Inc.

Case Details

Full title:Greystone Building & Development Corp., Plaintiff-Appellant, v. Makro…

Court:Appellate Division of the Supreme Court of the State of New York

Date published: Mar 10, 2020

Citations

181 A.D.3d 468 (N.Y. App. Div. 2020)
181 A.D.3d 468
2020 N.Y. Slip Op. 1584

Citing Cases

Turner Constr. Co. v. Nastasi & Assocs.

The record contains no evidence to determine when the owners paid Turner, when the claims accrued, and…

Turner Constr. Co. v. Nastasi & Assocs.

The record contains no evidence to determine when the owners paid Turner, when the claims accrued, and…