From Casetext: Smarter Legal Research

DiMario v. Heeks

Supreme Court of Rhode Island
Feb 17, 1976
116 R.I. 44 (R.I. 1976)

Opinion

February 17, 1976.

PRESENT: Paolino, Acting C.J., Joslin and Kelleher, JJ.

1. CONTRACTS. Building Contracts. Lock of Substantial Performance by Builder. Right of Recovery for Balance Due. A contractor cannot recover on a building contract unless he has substantially performed and any lesser degree of performance will not suffice.

2. CONTRACTS. Building Contracts. Evaluation of Contractor's Performance. Test of Substantial Performance. The evaluation of a contractor's performance on the basis of whether enumeration of deficiencies and a labelling of them collectively as unsubstantial fails to recognize that the evaluation of a contractor's performance as substantial or unsubstantial is not simple but rather is "a matter of degree,"' which should be measured "relatively to all the other complex factors" in a case.

3. EVIDENCE. Determination of Trial Justice. Evidentiary Support Issue. Appellate court could not determine the validity of the trial justice's determination that building contractor did not substantially perform lacking a careful quantitative and qualitative comparison between what was done and what should have been done, hence, where there was a failure of a relative determination process that deprived the conclusion of the trial justice that there was unsubstantial performance it lacked the support required to the weight ordinarily entitled on review.

4. EVIDENCE. Observations Resulting from View. Effect on Decision. What the trial justice observed on a view of the job site should not be utilized for finding the contractor guilty of a material breach of building contract.

CIVIL ACTION and MISCELLANEOUS PETITION involving claim of balance due under building contract and defense and counterclaim of defendant, before Supreme Court on appeals of plaintiff-contractor filed following judgment pursuant to decision of McKiernan, J. of Superior Court, heard and appeals of plaintiff sustained, judgments reversed and cases remitted to Superior Court for further proceedings.

Abatuno Chisholm, Thomas F. Fogarty, Jr., Howard L. Feldman, for plaintiff.

Alton W. Wiley, for defendants.


The plaintiff-contractor agreed in writing to remodel and build an addition to the defendant-owners' residence for approximately $10,745 of which all but $3,185 has been paid. When the owners refused to pay that balance, the contractor commenced two suits in the Superior Court. One was a civil action to recover the balance due on the contract; the other a miscellaneous petition to enforce a mechanics' lien for labor and materials furnished. The owners defended on the ground that the contractor was guilty of a material breach and, in addition, counterclaimed for the cost of making good the contractor's alleged failure to perform as promised.

Super. R. Civ. P. 81(a)(1) provides that the Rules of Civil Procedure are inapplicable during the process and pleading stages of petitions for the enforcement of mechanics' liens.

The contractor's two suits and the owners' counterclaim were heard without a jury by a trial justice who found in essence that the contractor's performance, though complete, was so unworkmanlike and defective as to constitute less than substantial performance of his obligations and that the owners were therefore justified in refusing to pay the final installment due on the building contract. He further found that notwithstanding the contractor's material breach, the owners had not produced any probative evidence of the cost of making good the contractor's defaults and hence were entitled to no more than nominal damages on their counterclaim.

Only the contractor has appealed, and his sole contention, as we understand it, is that the owners' failure to establish their right to anything but nominal damages entitles him, irrespective of whether he substantially performed, to a judgment for the balance due on the contract less the $200 he conceded to be the sum required to make his performance full and exact. The flaw in this argument is, of course, that a contractor cannot recover on a building contract unless he has substantially performed and that any lesser degree of performance will not suffice. Ferris v. Mann, 99 R.I. 630, 636, 210 A.2d 121, 124 (1965); see Carpenter v. Gay, 12 R.I. 306, 307-08 (1879).

There are jurisdictions which permit a contractor, even though he has not substantially performed, to recover, not on the contract itself, but for the reasonable value of his performance less the owners' damages. Britton v. Turner, 6 N.H. 481 (1834); Kirkland v. Archbold, 68 Ohio L. Abs. 481, 113 N.E.2d 496 (Ct. App. 1953).

For the contractor to recover in the civil action depends, then, upon whether he has substantially performed his contract, and not upon what the owners may prove on their counterclaim. On that score the trial justice specifically found that the contractor's work on the stairway, the dormer and the bathroom was defective; that the old structure had not been properly aligned with the new; and that because of those shortcomings, the contract had not been substantially performed. But a mere enumeration of deficiencies and a labelling of them collectively as unsubstantial fails to recognize that the evaluation of a contractor's performance as substantial or unsubstantial is not simple but rather is "a matter of degree," and should be made "relatively to all the other complex factors" in a case. 3A Corbin, Contracts § 704 at 318 (1960).

Here the trial justice's determination that the contractor did not substantially perform should therefore have been based upon a more thorough consideration of the extent and degree of nonperformance. This does not mean that there will not be instances where the work remaining to be done is so extensive or the quality of what has been done so poor that the performance may rather easily be characterized as unsubstantial, cf. Ferris v. Mann, supra at 636, 210 A.2d at 124. Nothing in the trial justice's bench decision or the parties' briefs or oral arguments, however, points to anything in the transcript or the exhibits indicating that this is such a case. Instead this case, like most cases, necessitated a careful quantitative and qualitative comparison between what was done and what should have been done. Nonetheless, the trial justice neglected to relate the work he found improperly performed to the total promised performance. Additionally, he rejected as lacking in probative force the owners' evidence of the cost of a partial curing of the deficiencies and thereby prevented any comparison between that cost and the total contract price. In short, he failed to engage in the relative determination process and in our judgment that omission deprives his ultimate conclusion of unsubstantial performance of the kind of evidentiary support it requires to entitle it to great weight on review.

The owners' witness testified to the effect that the carpentry work would cost between approximately $850 and $2,100, depending on the hourly wage, which might range from $3.50 to $7.00 for nonunion labor, and $8.76 for a union carpenter. This amount was exclusive of the necessary electrical, plumbing and other repairs.

In Ferris v. Mann, 99 R.I. 630, 210 A.2d 121 (1965), we held in effect that the total cost of completing work undone and rectifying work improperly done should have been considered in determining whether there had been substantial performance.

The trial justice also discounted the testimony introduced by plaintiff indicating that $200 would be sufficient to remedy performance. This testimony was premised on contractual modifications which the trial justice found had not been made.

Moreover, his specific findings of improper performance appear to rest, at least in part, upon what he observed on a view of the job site, rather than upon the testimony of witnesses, and to that extent his conclusion that the contractor was guilty of a material breach is not validly predicated. Corrado v. Providence Redev. Agency, 110 R.I. 549, 556-57, 294 A.2d 387, 390-91 (1972); D'Acchioli v. Cairo, 87 R.I. 345, 350, 141 A.2d 269, 272 (1958).

In these peculiar circumstances it seems to us that there must be a remand of the civil action to the trial court for a redetermination of the question of substantiality in the light of the relative extent, degree and value of the improper performance. If that redetermination results in establishing that the contractor substantially performed, he may recover the contract price, less a fair allowance to the owner for defective work. 6 Williston, Contracts § 842 at 167 (3d ed. 1962). While the trial justice dismissed the petition for the enforcement of a mechanics' lien, he made no findings whatsoever in connection therewith and indeed did not even discuss it. Hence, that petition, too, must be retried.

The plaintiff's appeals are sustained, the judgments appealed from are reversed, and the cases are remitted to the Superior Court for further proceedings.

Mr. Chief Justice Roberts participated in the argument but retired prior to the announcement of the decision. Mr. Justice Doris did not participate.


Summaries of

DiMario v. Heeks

Supreme Court of Rhode Island
Feb 17, 1976
116 R.I. 44 (R.I. 1976)
Case details for

DiMario v. Heeks

Case Details

Full title:ADOLPH DiMARIO vs. RALPH W. HEEKS et ux

Court:Supreme Court of Rhode Island

Date published: Feb 17, 1976

Citations

116 R.I. 44 (R.I. 1976)
351 A.2d 837

Citing Cases

Desimone Electric Inc. v. CMG, Inc., 01-6077 (2004)

It is well-settled that a contractor who substantially performs may recover the contract price, minus "a fair…

Russell v. Salve Regina College

The Rhode Island Supreme Court specifically has applied this doctrine in the construction contract context.…