Accent Commercial Furniture, Inc. v. Schneider & Associates

Supreme Court, Appellate Division, Third Department, New York.
Oct 31, 2013
110 A.D.3d 1415 (N.Y. App. Div. 2013)

Opinion

2013-10-31

ACCENT COMMERCIAL FURNITURE, INC., Respondent, v. P. SCHNEIDER & ASSOCIATES, PLLC, Appellant.

Cerio Law Offices, Syracuse (Thomas J. Cerio of counsel), for appellant. Roemer, Wallens & Mineaux, LLP, Albany (Matthew J. Kelly of counsel), for respondent.



Cerio Law Offices, Syracuse (Thomas J. Cerio of counsel), for appellant. Roemer, Wallens & Mineaux, LLP, Albany (Matthew J. Kelly of counsel), for respondent.
Before: STEIN, J.P., McCARTHY, SPAIN and EGAN JR., JJ.

McCARTHY, J.

Appeal from an order of the Supreme Court (McNamara, J.), entered September 27, 2012 in Albany County, which partially granted plaintiff's motion for summary judgment.

In September 2010, the parties entered into an oral contract for plaintiff to deliver and install furniture and wall panels in defendant's new office. Although defendant desired to have the installation completed in October 2010, the parties discovered when the furniture arrived that the manufacturer had used the incorrect fabric on the panels. The correct panels arrived in late December 2010 and were apparently installed in early January 2011. Plaintiff sent defendant an invoice dated January 4, 2011. Defendant had previously made a down payment, but did not make any payments after receiving the invoice. In January 2012, plaintiff commenced this action seeking to collect the remainder of its bill. Defendant counterclaimed, seeking damages for plaintiff's alleged breach of contract due to the late delivery. Plaintiff moved for summary judgment on its claims and to dismiss defendant's counterclaim. Supreme Court granted plaintiff summary judgment on its breach of contract cause of action and dismissed the part of defendant's counterclaim seeking two months rent. Defendant appeals.

Defendant also alleged that plaintiff's breach of the contract caused defendant damages related to installing cables and wires. Supreme Court denied the part of plaintiff's summary judgment motion seeking dismissal of this portion of the counterclaim, which is not at issue on appeal.

Supreme Court did not err in granting plaintiff summary judgment on its breach of contract cause of action. Because the transaction predominantly involved the sale of goods, the parties' rights and remedies are governed by UCC article 2 ( see Sears, Roebuck & Co. v. Galloway, 195 A.D.2d 825, 826, 600 N.Y.S.2d 773 [1993] ). The parties' oral contract is enforceable because both parties acknowledge the existence of that contract ( seeUCC 2–201[3] [b] ). The UCC provides that acceptance of goods takes place, among other ways, when the buyer fails to reject them after having a reasonable opportunity to inspect them ( seeUCC 2–606[1][b]; Sears, Roebuck & Co. v. Galloway, 195 A.D.2d at 826, 600 N.Y.S.2d 773;B. Milligan Contr. v. Mancini Assoc., 174 A.D.2d 136, 138, 578 N.Y.S.2d 931 [1992] ). A buyer must pay for accepted goods at the contract rate ( seeUCC 2–607[1] ), but may eliminate or diminish the amount claimed by a seller by asserting a valid counterclaim for breach of the sales agreement ( see Created Gemstones v. Union Carbide Corp., 47 N.Y.2d 250, 255, 417 N.Y.S.2d 905, 391 N.E.2d 987 [1979];Flick Lbr. Co. v. Breton Indus., 223 A.D.2d 779, 780, 636 N.Y.S.2d 169 [1996];B. Milligan Contr. v. Mancini Assoc., 174 A.D.2d at 138, 578 N.Y.S.2d 931). Where a seller has allegedly breached the contract, a buyer who has accepted the goods “must withina reasonable time after he [or she] discovers or should have discovered any breach notify the seller of breach or be barred from any remedy” (UCC 2–607[3][a]; see Sears, Roebuck & Co. v. Galloway, 195 A.D.2d at 827, 600 N.Y.S.2d 773).

Plaintiff met its burden on the summary judgment motion by submitting proof that it delivered and installed the furniture, defendant accepted the furniture by retaining it without attempting to return it, and defendant only paid the $13,250 down payment on the $44,330.21 contract ( seeUCC 2–606 [1]; Sears, Roebuck & Co. v. Galloway, 195 A.D.2d at 827, 600 N.Y.S.2d 773;Maggio Importato, Inc. v. Cimitron Inc., 189 A.D.2d 654, 654, 592 N.Y.S.2d 325 [1993],lv. denied82 N.Y.2d 652, 601 N.Y.S.2d 582, 619 N.E.2d 660 [1993];B. Milligan Contr. v. Mancini Assoc., 174 A.D.2d at 138, 578 N.Y.S.2d 931). Defendant does not dispute the amount that it has paid, that the furniture was delivered and that it has not been returned. Defendant only argues that it is entitled to an offset for rent and other costs allegedly incurred due to plaintiff's late delivery, which allegedly prevented defendant from occupying the new office for several months ( seeUCC 2–714). We will assume, for purposes of this motion and giving defendant the most favorable view of the evidence, that delivery before November 2010 was a material term of the contract. Defendant contends that, during a November 1, 2010 meeting, it provided sufficient notice to plaintiff regarding the breach of this condition. Even if this oral communication to plaintiff's non-managerial representatives constituted proper and timely notice of a breach of a material term of the contract, defendant could only recover causally-related consequential damages “which could not reasonably be prevented by cover or otherwise” (UCC 2–715[2][a] ).

Defendant does not address how it “attempt[ed] to minimize [its] damages in good faith, either by cover or otherwise” (UCC 2–715, Comment 2). Although defendant's managing member averred that the “delay rendered [d]efendant's office space unusable,” she did not elaborate or explain how it was unusable. Plaintiff's chief executive officer averred that plaintiff offered to install the furniture and panels with the incorrect fabric while waiting for the correct panels to arrive, at which time plaintiff would replace the fabric outside of defendant's business hours, but defendant declined this offer. In its response to the motion, defendant failed to assert that it made any effort to cover or minimize its damages, and did not address plaintiff's assertion that defendant declined plaintiff's offer to install furniture and panels that were fully functional—even if made with the incorrect fabric—in the interim, leaving no evidence that defendant's damages could not have been prevented ( seeUCC 2–715[2][a]; see also V. Zappala & Co. v. Pyramid Co. of Glens Falls, 81 A.D.2d 983, 984, 439 N.Y.S.2d 765 [1981],lv. denied55 N.Y.2d 603, 447 N.Y.S.2d 1025, 431 N.E.2d 643 [1981] ). Accordingly, Supreme Court properly granted plaintiff summary judgment on its breach of contract cause of action and dismissed the portion of the counterclaim seeking two months rent.

ORDERED that the order is affirmed, with costs.

STEIN, J.P., SPAIN and EGAN JR., JJ., concur.




Summaries of

Accent Commercial Furniture, Inc. v. Schneider & Associates

Supreme Court, Appellate Division, Third Department, New York.
Oct 31, 2013
110 A.D.3d 1415 (N.Y. App. Div. 2013)
Case details for

Accent Commercial Furniture, Inc. v. Schneider & Associates

Case Details

Full title:ACCENT COMMERCIAL FURNITURE, INC., Respondent, v. P. SCHNEIDER …

Court:Supreme Court, Appellate Division, Third Department, New York.

Date published: Oct 31, 2013

Citations

110 A.D.3d 1415 (N.Y. App. Div. 2013)
110 A.D.3d 1415
2013 N.Y. Slip Op. 7106

Citing Cases

KSW Mechanical Services v. Johnson Controls, Inc.

Moreover, the cases discussed by JCI concern situations involving delay, an issue listed in the description…

DS-Concept Trade Invest LLC v. Atalanta Corp.

Moreover, even if goods were delivered and accepted, U.C.C. § 2-717 allows a buyer who accepted…