From Casetext: Smarter Legal Research

Wilson v. Post-Tensioned Structures

District Court of Appeal of Florida, Third District
Mar 8, 1988
522 So. 2d 79 (Fla. Dist. Ct. App. 1988)

Summary

finding a condition precedent in contract stating that "final payment is contingent upon payment to the Contractor" and that "[i]n the event a controversy occurs between the Owner and the General Contractor concerning the Contract with the Owner . . . no compensation for these items shall be due the Subcontractor from the Contractor until payment for them is received by the Contractor"

Summary of this case from Midamerica Construction Management, Inc. v. MasTec North America, Inc.

Opinion

No. 87-1031.

March 8, 1988.

Appeal from the Circuit Court, Dade County, Michael Salmon, J.

M. Daniel Hughes, Ft. Lauderdale, for appellants.

Siegfried, Kipnis, Rivera, Lerner De La Torre and Samuel B. Reiner and Mark Greenberg, Coral Gables, for appellee.

Before HUBBART, BASKIN and DANIEL S. PEARSON, JJ.


This is an appeal by the defendant general contractor from an adverse final judgment entered against it after a non-jury trial in a breach of contract action brought below by the plaintiff subcontractor. We reverse based on a holding that the following provisions of the construction subcontract between the parties:

"When all work has been finally accepted by the Architect and WILSON/WOODCRAFT, final payment is contingent upon payment to the Contractor and shall be made within thirty (30) days after said payment from the Owner, provided the Subcontractor has previously furnished complete releases of lien and evidence of paid material bills"

Condition 34 of the subcontract (emphasis added), and

"No Change Orders will be issued for additional work of any kind unless so approved by the Architect and Owner prior to its issuance. In the event a controversy occurs between the Owner and the General Contractor concerning the Contract with the Owner or these Change Order(s), then it is expressly agreed that no compensation for these items shall be due the Subcontractor from the Contractor until payment for them is received by the Contractor, regardless of the fact that payment is delayed due to the Contractor negotiating with the Owner, arbitration, administrative actions, litigation, appeals or other similar activities"

Condition 20 of the subcontract (emphasis added), plainly and unambiguously make payment by the owner to the general contractor a condition precedent to payment by the contractor to the subcontractor herein, rather than merely fix a time for payment to the subcontractor. It is settled that the parties, as here, may so provide in their contract and thus shift the risk of the aforesaid payment failure by the owner from the general contractor to the subcontractor. Peacock Constr. Co. v. Modern Air Conditioning, Inc., 353 So.2d 840, 842 (Fla. 1977).

Because it is undisputed that the owner has not yet made payment under its contract with the general contractor, and that these two parties are currently engaged in litigation concerning this non-payment, it was error for the trial court to require the general contractor to pay under its contract with the subcontractor herein. The final judgment under review is, accordingly, reversed, and the cause is remanded to the trial court with directions to dismiss the instant action as being prematurely filed.

Reversed and remanded.


Summaries of

Wilson v. Post-Tensioned Structures

District Court of Appeal of Florida, Third District
Mar 8, 1988
522 So. 2d 79 (Fla. Dist. Ct. App. 1988)

finding a condition precedent in contract stating that "final payment is contingent upon payment to the Contractor" and that "[i]n the event a controversy occurs between the Owner and the General Contractor concerning the Contract with the Owner . . . no compensation for these items shall be due the Subcontractor from the Contractor until payment for them is received by the Contractor"

Summary of this case from Midamerica Construction Management, Inc. v. MasTec North America, Inc.
Case details for

Wilson v. Post-Tensioned Structures

Case Details

Full title:ROBERT F. WILSON, INC. AND WOODCRAFT INDUSTRIES, INC., BOTH D/B/A…

Court:District Court of Appeal of Florida, Third District

Date published: Mar 8, 1988

Citations

522 So. 2d 79 (Fla. Dist. Ct. App. 1988)

Citing Cases

Statesville Roofing Heating v. Duncan

Defendant cites one majority-view case as supporting the result he urges. To the contrary, it appears to…

Bentley Const. Dev. v. All Phase Elec

See Peacock (final payment to subcontractors to be made "within thirty days after the completion of the work…