From Casetext: Smarter Legal Research

St. Augustine Pools, Inc. v. Barker

District Court of Appeal of Florida, Fifth District
Feb 14, 1997
687 So. 2d 957 (Fla. Dist. Ct. App. 1997)

Summary

finding that general contract with arbitration provision was not incorporated by reference into parties' separate contract: "This Agreement is subject to the General Contract between the Owner and General Contractor. Subcontractor acknowledges that he is familiar with the General Contract and the General Conditions thereof and agrees to comply with all applicable provisions thereof."

Summary of this case from Ron v. Parrado

Opinion

Case No. 96-2210

Opinion filed February 14, 1997

Non-Final Appeal from the Circuit Court for St. Johns County, Robert K. Mathis, Judge.

Geoffrey B. Dobson of Dobson Brown, P.A., St. Augustine, for Appellant.

B. Thomas Whitefield of Ulmer, Murchison, Ashby Taylor, Jacksonville, for Appellee.


This is an appeal from an order in which the trial court denied appellant's motion for arbitration. We hold that the subcontractor agreement did not incorporate the arbitration agreement in the general contract. Further, we hold the general contract does not confer on appellant the right to arbitration.

Appellee constructed the Ocean Villas Condominium and subcontracted the construction of different parts of the project out to various companies. Appellant received the contract to install a pool and a cool deck. In October 1995, the Ocean Villas Condominium Association filed a complaint against appellee alleging that it breached various warranties, violated applicable building codes and breached its fiduciary responsibility. Appellee, in turn, filed an amended third-party complaint against a number of other companies including appellant. The claim against appellant stated the company constructed the cool deck and the pool in a deficient manner. Appellant filed a motion to dismiss the amended third-party complaint or, in the alternative, to abate or transfer. It argued that the lawsuit was subject to arbitration. The trial court denied appellant's motion.

Appellant argues two points on appeal. First, it maintains its contract with appellee incorporates by reference the provisions of the general contract containing an arbitration clause. Second, it asserts it is a third-party beneficiary to the general contract and thus entitled to enforce the arbitration clause. We disagree.

The first issue is resolved by interpreting the appropriate section of the subcontract or agreement to determine whether it incorporates the terms of the general contract. Paragraph 16 of the agreement states in relevant part:

16. This Agreement is subject to the General Contract between the Owner and General Contractor. Subcontractor acknowledges that he is familiar with the General Contract and the General Conditions thereof and agrees to comply with all applicable provisions thereof.

The term "subject to" means "liable, subordinate, subservient, inferior, obedient to; governed or affected by; provided that; provided; answerable." Black's Law Dictionary 1425 (6th ed. 1990); See also, Homan v. Employers Reins. Corp., 136 S.W.2d 289 (Mo. 1939). The words "subject to" "usually indicate a condition to one party's duty of performance and not a promise by the other." Burgess Constr. Co. v. M. Morrin Son Co., Inc., 526 F.2d 108, 113 (10th Cir. 1975), cert. den., 429 U.S. 866, 97 S.Ct. 176, 50 L.Ed.2d 146 (1976) (citing Am.Jur.2d Contracts § 320 (1964)). Applying these definitions to the subcontractor agreement it is clear that the intent of the parties was to not incorporate the arbitration language of the general contract into the subcontract.

The guiding force in the interpretation of contracts is to determine what the intent of the parties was. This phrase indicates that one party has a condition of performance and therefore the words serve to limit the contract. When read as a whole, paragraph 16 indicates that the general contract is referenced solely to make the subcontractor aware of its duties and requirements. The subcontractor does not have a duty or requirement to arbitrate any disagreements. The language of paragraph 15 establishes that the parties' intention was that "any claim or cause of action against the Contractor or Owner arising out of, in connection with, or by virtue of the relationship created by this Agreement, shall be brought and filed in . . . and shall be heard by a judge of the appropriate court therein." In regard to the second issue, appellant relies on section 5.3.1 of the general conditions of the contract to demonstrate that it is allowed the right to arbitration. Section 5.3.1 provides in pertinent part:

5.3.1 By an appropriate agreement, written where legally required for validity, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by the terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities which the Contractor, by these Documents, assumes toward the Owner and the Architect. Said agreement shall preserve and protect the rights of the Owner and the Architect under the Contract Documents with respect to the Work to be performed by the Subcontractor so that the subcontracting thereof will not prejudice such rights, and shall allow to the Subcontractor, unless specifically provided otherwise in the Contractor-Subcontractor agreement, the benefit of all rights, remedies, and redress against the contractor that the Contractor, by these Documents, has against the Owner. [emphasis added]

This language, when read as a whole, does not confer the right to arbitration upon appellant. Appellee correctly points out that paragraph 15 of the subcontractor agreement provides that any dispute shall be brought in court. Therefore this section does not confer on appellant the right to arbitration.

AFFIRMED.

GRIFFIN and ANTOON, JJ., concur.


Summaries of

St. Augustine Pools, Inc. v. Barker

District Court of Appeal of Florida, Fifth District
Feb 14, 1997
687 So. 2d 957 (Fla. Dist. Ct. App. 1997)

finding that general contract with arbitration provision was not incorporated by reference into parties' separate contract: "This Agreement is subject to the General Contract between the Owner and General Contractor. Subcontractor acknowledges that he is familiar with the General Contract and the General Conditions thereof and agrees to comply with all applicable provisions thereof."

Summary of this case from Ron v. Parrado

In St. Augustine Pools, Inc. v. James M. Barker, Inc., 687 So.2d 957, 958 (Fla. 5th DCA 1997), the court examined a subcontract that was "subject to the General Contract" and provided that "Subcontractor acknowledges that he is familiar with the General Contract and the General Conditions thereof andagrees to comply with all applicable provisions thereof."

Summary of this case from ETIENNE v. HANG TOUGH, INC.

defining "subject to" as "liable, subordinate, subservient, inferior, obedient to; governed or affected by; provided that; provided; answerable" (quoting Black's Law Dictionary 1425 (6th. ed. 1990))

Summary of this case from Uoweit, LLC v. Fleming

defining "subject to" as "liable, subordinate, subservient, inferior, obedient to; governed or affected by; provided that; provided; answerable"

Summary of this case from Allstate Fire & Casualty Insurance v. Stand-Up MRI of Tallahassee, P.A.

In St. Augustine Pools, Inc. v. James M. Barker, Inc., 687 So.2d 957 (Fla. 5th DCA 1997), the court considered a similar issue in the context of a contract between a general contractor ("GC") and a subcontractor.

Summary of this case from Affinity Internet v. Conso. Credit
Case details for

St. Augustine Pools, Inc. v. Barker

Case Details

Full title:ST. AUGUSTINE POOLS, INC., Appellant, v. JAMES M. BARKER, INC., Appellee

Court:District Court of Appeal of Florida, Fifth District

Date published: Feb 14, 1997

Citations

687 So. 2d 957 (Fla. Dist. Ct. App. 1997)

Citing Cases

U.S. v. Interface Construction Corp.

Another court that considered this issue found that language in the subcontract making it "subject to the…

Uoweit, LLC v. Fleming

Wellness & Rehab. v. Allstate Fire & Cas. Ins. Co. , 201 So. 3d 169, 172 (Fla. 3d DCA 2016) ("[T]he phrase…