From Casetext: Smarter Legal Research

Primax Props., LLC v. Monument Agency, Inc.

Supreme Court, Appellate Division, Fourth Department, New York.
Feb 9, 2018
158 A.D.3d 1336 (N.Y. App. Div. 2018)

Summary

granting plaintiff specific performance of his real estate agreement where he repeatedly indicated that he was willing, ready and able to close by the required date, and the defendant repeatedly ignored plaintiff's letters

Summary of this case from Consol. Edison Co. of N.Y., Inc. v. Cantor

Opinion

1329 CA 16–01844

02-09-2018

PRIMAX PROPERTIES, LLC, Plaintiff–Respondent, v. MONUMENT AGENCY, INC., Marlene Kernan, Waterbury Square, Inc., Formerly Known as 107 River Street, Inc., Defendants–Appellants, and Peter C. Earle, Defendant–Respondent.

KERNAN PROFESSIONAL GROUP, LLP, ORISKANY (JAMES M. KERNAN OF COUNSEL), AND KERNAN AND KERNAN, P.C., UTICA, FOR DEFENDANTS–APPELLANTS. MCNAMEE, LOCHNER, TITUS & WILLIAMS, P.C., ALBANY (SCOTT C. PATON OF COUNSEL), FOR PLAINTIFF–RESPONDENT. WOODRUFF LEE CARROLL, SYRACUSE, FOR DEFENDANT–RESPONDENT.


KERNAN PROFESSIONAL GROUP, LLP, ORISKANY (JAMES M. KERNAN OF COUNSEL), AND KERNAN AND KERNAN, P.C., UTICA, FOR DEFENDANTS–APPELLANTS.

MCNAMEE, LOCHNER, TITUS & WILLIAMS, P.C., ALBANY (SCOTT C. PATON OF COUNSEL), FOR PLAINTIFF–RESPONDENT.

WOODRUFF LEE CARROLL, SYRACUSE, FOR DEFENDANT–RESPONDENT.

PRESENT: SMITH, J.P., CENTRA, CURRAN, AND TROUTMAN, JJ.

MEMORANDUM AND ORDER

Memorandum:In 2014, plaintiff, a commercial real estate developer, entered into two separate real estate contracts with the intention of building a Dollar General store in the Village of Oriskany, New York. In the first contract, defendant Peter C. Earle agreed to sell plaintiff his entire parcel of land (hereafter, Earle parcel) in exchange for $190,000. In the second contract, defendant Monument Agency, Inc. (Monument), through its agent defendant Marlene Kernan, agreed to sell plaintiff a portion of a parcel neighboring the Earle parcel (hereafter, Monument parcel) for $10,000. As of March 20, 2015, plaintiff had fulfilled all of its obligations under the contract with Monument and sent Monument a letter indicating that it was ready to close. Plaintiff did not receive any response to that letter nor to any of its repeated phone calls requesting that Monument close on the contract. In April 2015, plaintiff sent two letters to Monument indicating that it remained ready, willing, and able to close, and demanding specific performance of the contract. After receiving no response from Monument, plaintiff filed the instant action against Monument, seeking, inter alia, specific performance of the contract. In its answer, Monument asserted as an affirmative defense that it was unable to close on the contract because the description of the property to be conveyed was incorrect.

Thereafter, plaintiff was forestalled from closing on the Earle parcel because of a claim made by another entity, defendant Waterbury Square, Inc., formerly known as 107 River Street, Inc. (Waterbury), that the Earle parcel was incorrectly described in the contract between plaintiff and Earle. Specifically, Waterbury stated that it had purchased land at a tax sale in 2014 (hereafter, Waterbury parcel), and that purchase included a portion of the land that Earle was attempting to sell to plaintiff. As a result, plaintiff amended its complaint to include Waterbury and Earle as defendants. Plaintiff then moved for partial summary judgment on its third cause of action, for specific performance of the contract with Monument, and on its sixth cause of action, seeking a declaration as to the location of the boundary line between the Waterbury parcel and the Earle parcel. Supreme Court, inter alia, granted plaintiff's motion, ordered that Monument fulfill its obligations under the contract and issued a declaration that the boundary line between the Earle parcel and the Waterbury parcel is the same boundary line as is set forth in the survey of plaintiff's expert surveyor. Waterbury, Kernan and Monument (hereafter, defendants) appeal.

Contrary to defendants' contention, the court properly awarded plaintiff specific performance of the contract with Monument. "To obtain summary judgment for specific performance of a real estate contract, [the] plaintiff must ‘demonstrate that [it] substantially performed [its] contractual obligations and [was] ready, willing and able to fulfill [its] remaining obligations, [and] that [the] defendant was able but unwilling to convey the property’ " ( Fallati v. Mackey, 31 A.D.3d 879, 880, 818 N.Y.S.2d 341 [3d Dept. 2006], lv denied 7 N.Y.3d 711, 824 N.Y.S.2d 603, 857 N.E.2d 1134 [2006] ; see Pasquarella v. 1525 William St., LLC, 120 A.D.3d 982, 983, 990 N.Y.S.2d 760 [4th Dept. 2014] ). Here, plaintiff presented evidence establishing that it sent Monument three letters stating that it was ready, willing, and able to close, and that Monument failed to respond to those letters or to close on the transaction. Plaintiff further submitted the affidavit of an expert surveyor, who opined that the boundary line between the Earle parcel and the Monument parcel was the same as described in the contract with Monument. Moreover, plaintiff submitted the affidavit of a title researcher, who reviewed the parcels' deeds, title commitment paperwork, and tax maps, and agreed with the expert surveyor's opinion. Therefore, we conclude that plaintiff met its burden of establishing its entitlement to specific performance of the contract with Monument, and that the burden then shifted to defendants "to produce evidentiary proof in admissible form sufficient to raise a material issue of fact to avoid summary judgment" ( Fallati, 31 A.D.3d at 880, 818 N.Y.S.2d 341 ; see Bergstrom v. McChesney, 92 A.D.3d 1125, 1126, 938 N.Y.S.2d 663 [3d Dept. 2012] ; see also Piekunka v. Straubing, 149 A.D.3d 1483, 1483–1484, 53 N.Y.S.3d 743 [4th Dept. 2017] ).

In response, defendants submitted the affidavit of a title researcher who did not survey the relevant parcels, but who opined that plaintiff's expert surveyor had incorrectly relied on the tax maps of the parcels when conducting his survey. Defendants also submitted the affidavit of their expert surveyor, who did not survey the parcels and offered no criticisms of the work of plaintiff's surveyor. We conclude that, without a competing survey accompanied by an affidavit of a surveyor, defendants failed to raise a triable question of fact (see Piekunka, 149 A.D.3d at 1484, 53 N.Y.S.3d 743 ; see also City of Binghamton v. T & K Communications Sys., 290 A.D.2d 797, 799, 736 N.Y.S.2d 496 [3d Dept. 2002], lv dismissed 98 N.Y.2d 685, 746 N.Y.S.2d 687, 774 N.E.2d 752 [2002], rearg. denied 98 N.Y.2d 728, 749 N.Y.S.2d 478, 779 N.E.2d 189 [2002] ; see generally Bergstrom, 92 A.D.3d at 1126–1127, 938 N.Y.S.2d 663 ), and the court therefore properly granted that part of plaintiff's motion seeking specific performance of the Monument contract.

We reject defendants' further contention that the court erred granting that part of plaintiff's motion seeking a declaration with respect to the boundary line between the Waterbury parcel and the Earle parcel. It is well settled that, "[t]o prevail in a proceeding pursuant to RPAPL article 15, a party must demonstrate good title in itself; it may not rely on the weakness of its adversary's title" ( LaSala v. Terstiege, 276 A.D.2d 529, 530, 713 N.Y.S.2d 767 [2d Dept. 2000] ; see State of New York v. Moore, 298 A.D.2d 814, 815, 751 N.Y.S.2d 321 [3d Dept. 2002] ; see generally Mazzoni v. Village of Seneca Falls, 68 A.D.3d 1805, 1806, 891 N.Y.S.2d 782 [4th Dept. 2009] ). Here, plaintiff established through expert affidavits that Earle had good title to the Earle parcel, as that parcel is described in the Earle contract, and defendants failed to raise a triable issue of fact (see Bergstrom, 92 A.D.3d at 1126–1127, 938 N.Y.S.2d 663 ; T & K Communications Sys., 290 A.D.2d at 799, 736 N.Y.S.2d 496 ).

We have considered defendants' remaining contentions and conclude that they are without merit.

It is hereby ORDERED that the order and judgment so appealed from is unanimously affirmed without costs.


Summaries of

Primax Props., LLC v. Monument Agency, Inc.

Supreme Court, Appellate Division, Fourth Department, New York.
Feb 9, 2018
158 A.D.3d 1336 (N.Y. App. Div. 2018)

granting plaintiff specific performance of his real estate agreement where he repeatedly indicated that he was willing, ready and able to close by the required date, and the defendant repeatedly ignored plaintiff's letters

Summary of this case from Consol. Edison Co. of N.Y., Inc. v. Cantor
Case details for

Primax Props., LLC v. Monument Agency, Inc.

Case Details

Full title:PRIMAX PROPERTIES, LLC, Plaintiff–Respondent, v. MONUMENT AGENCY, INC.…

Court:Supreme Court, Appellate Division, Fourth Department, New York.

Date published: Feb 9, 2018

Citations

158 A.D.3d 1336 (N.Y. App. Div. 2018)
2018 N.Y. Slip Op. 1020
71 N.Y.S.3d 302

Citing Cases

Consol. Edison Co. of N.Y., Inc. v. Cantor

"To obtain summary judgment for specific performance of a real estate contract, the plaintiff must…

Torre v. Town of Tioga

The court correctly found that defendants failed to prove that Deutsch's credentials as a title researcher…