Summary
holding that there is "no expectation of payment" where a "plaintiff may have performed preparatory work in anticipation of and to facilitate a successful contract negotiation"
Summary of this case from Hudson & Broad, Inc. v. J.C. Penney Corp.Opinion
146
February 11, 2003.
Appeal from order, Supreme Court, New York County (Herman Cahn, J.), entered on or about February 6, 2002, granting the motion of defendant Citnalta Construction Corp. (Citnalta) for summary judgment dismissing the complaint, deemed, pursuant to CPLR 5501(c), an appeal from the ensuing judgment, same court and Justice, entered on or about February 26, 2002, dismissing the complaint, the judgment unanimously affirmed, without costs.
Mark Seiden, for plaintiff-appellant.
Gary N. Weintraub, for defendants-respondents.
Before: Mazzarelli, J.P., Andrias, Saxe, Buckley, Friedman, JJ.
Plaintiff's breach of contract claim was properly dismissed since it is undisputed that the parties were aware that there would be no binding agreement until their execution of a written subcontract, which never occurred (see Scheck v. Francis, 26 N.Y.2d 466, 469-470). Indeed, plaintiff's return of the proposed subcontract to Citnalta with significant modifications, including a change as to the price for its services, constituted a counteroffer, and, as such, a rejection of Citnalta's offer (see Homayouni v. Paribas, 241 A.D.2d 375, 376).
Nor was there any basis to sustain plaintiff's claim for recovery in quantum meruit since there is no triable issue as to whether plaintiff performed the services in question with any reasonable expectation of compensation (see Lehrer McGovern Bovis, Inc. v. New York Yankees, 207 A.D.2d 256). Plaintiff was aware that its right to compensation for the work that was the subject of the proposed subcontract depended upon the execution of a written contract, and plaintiff never billed Citnalta for any work. While plaintiff may have performed preparatory work in anticipation of and to facilitate a successful contract negotiation (see Absher Constr. Corp. v. Colin, 233 A.D.2d 279), under the circumstances it could have had no expectation of payment, except pursuant to a written contract.
We have considered plaintiff's remaining arguments and find them unavailing.
THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.